Systems in depth
One section per system: its state at evidence close, its exposures and what the operational series will watch.
Contents
- ·Edition home
- ·Executive summary
- 1AI compute is physical infrastructure built on a few chips and a few places
- 2Key findings
- 3Systems and sectors at baseline
- 4Risks and capability
- 5Compute build-out meets local power, water and packaging limits
- 6Readings from the other desks
- 7The 2027 agenda
- 8Systems in depth
- AMethodology
- BData appendix
- CReferences and record
- ·Complete edition, for print
8.1Compute hardware and fabrication
AI compute is built from advanced logic and memory chips made in a few clusters. Market figures are strong; counts of chips and capacity by place are thin.
| Component | State | Evidence | Status |
|---|---|---|---|
| Logic and memory | logic USD 301.9 billion and memory USD 223.1 billion of sales in 2025 | 8 | Reported |
| AI supercomputers | performance doubling about every nine months; one 2025 system used about 200,000 chips | 1 | Reported |
| Foundry concentration | press reports give the largest foundry nearly 70% of 2025 foundry sales; about 74% of its wafer revenue came from 7 nanometre and smaller nodes | 222728 | Reported |
| Vendor products | one vendor lists 208 billion transistors per accelerator on a custom 4NP process; a vendor claim | 19 | Reported |
Couplings
- INF ↔ FIN sales and plants
- AIC → INF demand
- TRD → INF controls
Evidence to bind in 2027
- chip and accelerator volumes by type
- fabrication capacity by country
Related editions
- GLB Global Systems
- GS-02 Energy
- SR-03 Global Supply Chains, Trade and Chokepoints
- SR-04 Critical Minerals and Strategic Materials
- XT-01 Artificial Intelligence and Agentic Systems
- XT-07 HPC and Advanced Computing
8.2Energy, power and water
Compute and fabrication need electricity and cooling water. US data centre use is documented; plant water use is reported by single companies.
| Component | State | Evidence | Status |
|---|---|---|---|
| Data centre electricity | US use 176 TWh in 2023, about 4.4% of national electricity | 1516 | Reported |
| Global data centre electricity | about 415 TWh in 2024 and about 945 TWh in 2030 in the IEA base case, from search summaries | 24 | Reported |
| Efficiency | hardware efficiency rose about 40% a year; sparse models can use under a tenth of the energy of dense ones | 57 | Reported |
| Fab water | one company reports about 5,300 acre-feet a year for one fab and a 65% reclamation rate | 23 | Reported |
Couplings
- AIC → ENE load growth
- ENE ↔ WAT cooling and process water
- ENE → CLI emissions
Evidence to bind in 2027
- plant and data centre water use
- global electricity series from the report itself
Related editions
- GLB Global Systems
- GS-02 Energy
- SR-03 Global Supply Chains, Trade and Chokepoints
- SR-04 Critical Minerals and Strategic Materials
- XT-01 Artificial Intelligence and Agentic Systems
- XT-07 HPC and Advanced Computing
8.3Equipment, memory and materials
Chips depend on specialised tools, memory stacks and minerals. Equipment billings are documented through a trade report; materials figures are not bound.
| Component | State | Evidence | Status |
|---|---|---|---|
| Equipment billings | USD 135.1 billion in 2025, up 15%; North America down 20% and Europe down 41% | 9 | Reported |
| Lithography | Moore observed doubling in 1965 and revised the pace in 1975; the equipment maker states EUV gives the highest resolution | 2036 | Reported |
| Memory | a high-bandwidth memory standard was published in 2025; details come from search summaries | 32 | Reported |
| Minor minerals | gallium and germanium are used in chips and concentrated in primary production; primary figures not bound | 252640 | Inferred |
Couplings
- TRD → INF tools and controls
- MIN → INF materials
- FIN → INF equipment spend
Evidence to bind in 2027
- packaging and memory capacity by country
- gallium and germanium figures from the primary source
Related editions
- GLB Global Systems
- GS-02 Energy
- SR-03 Global Supply Chains, Trade and Chokepoints
- SR-04 Critical Minerals and Strategic Materials
- XT-01 Artificial Intelligence and Agentic Systems
- XT-07 HPC and Advanced Computing
8.4Economy, investment and workforce
Sales and public programmes are large and well documented. Outlays and workforce numbers are the thin parts of the evidence.
| Component | State | Evidence | Status |
|---|---|---|---|
| Sales | USD 791.7 billion in 2025; about USD 1 trillion projected for 2026 by SIA | 8 | Reported |
| US programmes | USD 39 billion for manufacturing and USD 11 billion for research; award outlays not bound at the close | 4411 | Reported |
| EU programmes | more than EUR 33 billion across 19 State aid decisions; second act proposed June 2026 | 12 | Reported |
| Japan and India | Rapidus round of JPY 267.6 billion in 2026; India mission listed | 214243 | Reported |
Couplings
- FIN → INF plants and tools
- GOV → FIN subsidy flows
- HLT → INF workforce
Evidence to bind in 2027
- subsidy outlays against awards
- workforce size and skills gaps
Related editions
- GLB Global Systems
- GS-02 Energy
- SR-03 Global Supply Chains, Trade and Chokepoints
- SR-04 Critical Minerals and Strategic Materials
- XT-01 Artificial Intelligence and Agentic Systems
- XT-07 HPC and Advanced Computing
8.5Security, export controls and governance watch
Export controls and subsidies now shape the supply chain. Rules change at short notice, so the watch follows the rule texts.
| Component | State | Evidence | Status |
|---|---|---|---|
| US controls | licence required for advanced computing items to entities headquartered in Country Group D:5; Section 232 investigation listed | 13 | Reported |
| Diffusion rule | framework published in January 2025 and rescinded in May 2025, per law-firm summaries | 3031 | Reported |
| Allied controls | Netherlands and Japan control lithography equipment, cited from memory | 41 | Inferred |
| EU governance | three pillars and a European Semiconductor Board; second act proposed | 1233 | Reported |
Couplings
- TRD → INF controls
- GOV → FIN subsidy flows
- INF → DAT hardware supply
Evidence to bind in 2027
- text of the second Chips Act
- licence statistics
Related editions
- GLB Global Systems
- GS-02 Energy
- SR-03 Global Supply Chains, Trade and Chokepoints
- SR-04 Critical Minerals and Strategic Materials
- XT-01 Artificial Intelligence and Agentic Systems
- XT-07 HPC and Advanced Computing
Notes
Numbers are the edition’s reference numbers, so a note reads the same in every chapter. The full list, with every source and its licence, is in Annex C. Annex C, references
- 8Semiconductor Industry Association (ed.), Global Annual Semiconductor Sales Increase 25.6% to $791.7 Billion in 2025 (release; WSTS data; logic USD 301.9 billion; memory USD 223.1 billion; regional growth; about USD 1 trillion projected for 2026). Semiconductor Industry Association, Washington. Observation year 2025. Accessed 2026-11-03.back
- 1Pilz, K.F., Sanders, J., Rahman, R. and Heim, L., Trends in AI Supercomputers, arXiv:2504.16026, submitted 22 April 2025 (abstract page: 500 systems from 2019 to 2025; performance doubling about every nine months; cost and power doubling about every year; one March 2025 system with about 200,000 chips, USD 7 billion and 300 MW; about 75% of performance in the United States). arXiv, Ithaca. Observation year 2025. Accessed 2026-11-03.back
- 22Focus Taiwan, Central News Agency (ed.), report of 13 March 2026 on the largest foundry reaching almost 70% of the global foundry market in 2025 (headline and lead only; the rest is behind a paywall); press report, weak evidence. Central News Agency, Taipei. Observation year 2025. Accessed 2026-11-03.back
- 27UNVERIFIED, not opened: TrendForce (ed.), 2025 foundry ranking (largest foundry sales about USD 122.5 billion and a share of about 69.9%), taken from press coverage in search results. TrendForce, Taipei. Observation year 2025. Accessed 2026-11-03.back
- 28UNVERIFIED, not opened: TSMC (ed.), fourth-quarter 2025 results (about 74% of 2025 wafer revenue from 7 nanometre and smaller nodes against 69% in 2024), taken from press coverage in search results; sources differ on the quarterly share. Taiwan Semiconductor Manufacturing Company, Hsinchu. Observation year 2025. Accessed 2026-11-03.back
- 19Nvidia (ed.), Blackwell architecture product page (208 billion transistors per GPU; custom TSMC 4NP process; performance multiples are vendor claims and weak evidence). Nvidia, Santa Clara. Observation year 2026. Accessed 2026-11-03.back
- 15US Department of Energy (ed.), DOE Releases New Report Evaluating Increase in Electricity Demand from Data Centers, 20 December 2024 (176 TWh in 2023, about 4.4%; 325 to 580 TWh, about 6.7% to 12%, in 2028). US Department of Energy, Washington. Observation year 2023. Accessed 2026-11-03.back
- 3Sevilla, J. and others, Can AI scaling continue through 2030?, Epoch AI, 20 August 2024 (first 100,000 characters read: about 4 times a year; 1 to 5 GW campuses; about 2e29 FLOP feasible by 2030; power binds first). Epoch AI, San Francisco. Observation year 2024. Accessed 2026-11-03.back
- 16Shehabi, A. and others, 2024 United States Data Center Energy Usage Report, Lawrence Berkeley National Laboratory, December 2024 (publication page abstract only; no figures on the page; the report PDF was not read). Lawrence Berkeley National Laboratory, Berkeley. Observation year 2023. Accessed 2026-11-03.back
- 24UNVERIFIED, not opened: IEA (ed.), Energy and AI, April 2025 (about 415 TWh of global data centre electricity in 2024, about 1.5% of the total; about 945 TWh in 2030 in the base case; range of 700 to 1,700 TWh in 2035), taken from search-result summaries; the IEA pages returned an access error. International Energy Agency, Paris. Observation year 2024. Accessed 2026-11-03.back
- 5Stanford Institute for Human-Centered AI (ed.), The 2025 AI Index Report, key takeaways page (training compute doubling about every five months; hardware cost down about 30% a year; energy efficiency up about 40% a year; chips detail not given on the page). Stanford University, Stanford. Observation year 2025. Accessed 2026-11-03.back
- 7Patterson, D. and others, Carbon Emissions and Large Neural Network Training, arXiv:2104.10350, April 2021 (abstract page: sparse models under one tenth of the energy; location effect 5 to 10 times; choice of model, datacentre and processor 100 to 1000 times). arXiv, Ithaca. Observation year 2021. Accessed 2026-11-03.back
- 23AZFamily (ed.), TSMC Arizona expansion could make it Phoenix’s largest water customer, 22 July 2026 (total planned investment USD 265 billion; about 5,300 acre-feet a year for the first fab; 65% reclaimed; goal 90%); local news reporting company figures, weak evidence. Gray Media, Phoenix. Observation year 2026. Accessed 2026-11-03.back
- 9Evertiq (ed.), Semiconductor equipment billings reached $135B in 2025, 9 April 2026, a trade report of a SEMI release (USD 135.06 billion in 2025 against USD 117.14 billion in 2024; regional table); the SEMI page itself returned an access error, so this is a secondary report and weak evidence. Evertiq, Munich. Observation year 2025. Accessed 2026-11-03.back
- 20ASML (ed.), Moore’s law explainer page (Moore observation of 1965 and revision of 1975; statement that EUV gives the highest resolution; no High-NA content on the page). ASML, Veldhoven. Observation year 2026. Accessed 2026-11-03.back
- 36UNVERIFIED, not opened: Moore, G.E., Cramming more components onto integrated circuits, Electronics 38(8), 1965, cited from memory. Observation year 1965. Accessed 2026-11-03.back
- 32UNVERIFIED, not opened: JEDEC (ed.), JESD270-4 HBM4 standard, April 2025 (about 2 TB/s per stack; 32 channels; up to 64 GB per stack), taken from search-result summaries; the JEDEC page returned an access error. JEDEC Solid State Technology Association, Arlington. Observation year 2025. Accessed 2026-11-03.back
- 25UNVERIFIED, not opened: USGS (ed.), Mineral Commodity Summaries 2026, gallium chapter (reported in summaries as about 99% of primary low-purity gallium produced in China in 2025), taken from search-result summaries; the page returned an access error and no figure is used in the findings. US Geological Survey, Reston. Observation year 2025. Accessed 2026-11-03.back
- 26UNVERIFIED, not opened: USGS (ed.), Mineral Commodity Summaries 2026, germanium chapter, the page returned an access error; summaries differ on China shares and no figure is used. US Geological Survey, Reston. Observation year 2025. Accessed 2026-11-03.back
- 40UNVERIFIED, not opened: IEA (ed.), Global Critical Minerals Outlook 2026, cited from the XT-02 notes of this series, not read for this edition; no figure is used. International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 44United States Congress, CHIPS and Science Act, Public Law 117-167, enacted 9 August 2022 (text of section 102 on Congress.gov, first 100,000 characters read: the funding lines for sections 9902 and 9906 of Public Law 116-283 by fiscal year 2022 to 2026 sum to USD 39 billion for manufacturing incentives and USD 11 billion for research, USD 50 billion in all; the totals are sums of the listed amounts, not stated in the text). Observation year 2022. Accessed 2026-11-03.back
- 12European Commission (ed.), European Chips Act policy page (entered into force 21 September 2023; three pillars; more than EUR 33 billion across 19 State aid decisions; second Chips Act proposed June 2026). Directorate-General for Communications Networks, Content and Technology, Brussels. Observation year 2026. Accessed 2026-11-03.back
- 11NIST (ed.), CHIPS research and development programmes page (National Semiconductor Technology Center, National Advanced Packaging Manufacturing Program, Manufacturing USA institute; undated; no programme amounts). National Institute of Standards and Technology, Gaithersburg. Observation year 2026. Accessed 2026-11-03.back
- 21The Register (ed.), Japan’s Rapidus lands $1.7B to chase 2nm chip production by 2027, 27 February 2026 (JPY 267.6 billion round; JPY 100 billion from a METI agency; JPY 167.6 billion from 32 companies); trade press, weak evidence. Situation Publishing, London. Observation year 2026. Accessed 2026-11-03.back
- 42UNVERIFIED, not opened: Government of India, Ministry of Electronics and Information Technology, India Semiconductor Mission, the programme site returned an access error; cited from memory without figures. Observation year 2026. Accessed 2026-11-03.back
- 43UNVERIFIED, not opened: METI and press coverage of the April 2026 addition of JPY 631.5 billion to Rapidus support, bringing research and development support to about JPY 2.354 trillion, taken from search-result summaries; totals differ by source. Observation year 2026. Accessed 2026-11-03.back
- 13US Department of Commerce, Bureau of Industry and Security (ed.), home page and news items (May 2026 guidance on licences for advanced computing items to Country Group D:5 entities; 7 April 2026 extension of the authorised IC designer timeline to 31 December 2026; Section 232 investigation of semiconductor imports listed). BIS, Washington. Observation year 2026. Accessed 2026-11-03.back
- 30UNVERIFIED, not opened: US Department of Commerce, Framework for Artificial Intelligence Diffusion, interim final rule, 90 Federal Register 4544, January 2025, cited from search summaries; the Federal Register page redirected. Federal Register, Washington. Observation year 2025. Accessed 2026-11-03.back
- 31UNVERIFIED, not opened: law-firm client alerts on the rescission of the AI diffusion rule and related guidance, 12 and 13 May 2025, taken from search-result summaries; a formal notice date was not confirmed. Observation year 2025. Accessed 2026-11-03.back
- 41UNVERIFIED, not opened: Government of the Netherlands and Government of Japan, export-control rules on advanced semiconductor manufacturing equipment, 2023, cited from memory; no figure is used. Observation year 2023. Accessed 2026-11-03.back
- 33UNVERIFIED, not opened: European Union, Regulation (EU) 2023/1781 of 13 September 2023 establishing a framework of measures for strengthening Europe’s semiconductor ecosystem (Chips Act); the EUR-Lex fetch returned no text, cited from memory. Publications Office of the European Union, Luxembourg. Observation year 2023. Accessed 2026-11-03.back