Methodology
How the edition was made: methods, the model card, the evidence cut and its age, the acceptance record and the glossary.
Contents
- ·Edition home
- ·Executive summary
- 1Fusion is an experiment record and a fuel-cycle question
- 2Key findings
- 3Systems and sectors at baseline
- 4Risks and capability
- 5First-plant fuel and licence set the pace
- 6Readings from the other desks
- 7The 2027 agenda
- 8Systems in depth
- AMethodology
- BData appendix
- CReferences and record
- ·Complete edition, for print
A.1Methods
The global baseline uses published values and four simple derivations. Each is shown in full so that any reader can reproduce it.
| No. | Derivation | Calculation | Result |
|---|---|---|---|
| (1) | Target gain of the December 2022 NIF shot | 3.15 ÷ 2.05 | 1.54 |
| (2) | Start of deuterium-tritium operation in the 2016 ITER plan implied by a four-year delay to 2039 | 2039 minus 4 | 2035 |
| (3) | Average fusion power over the JET record pulse | 69 MJ ÷ 5 s | about 14 MW |
| (4) | Ratio of private funding in 12 months to July 2026 to the 2025 figure | 4.48 ÷ 2.64 | about 1.7 times |
| Strength | Definition |
|---|---|
| STRONG | a disruption in the source system has historically changed the target system’s service or output within one season, in more than one region |
| MODERATE | an effect is documented but buffered or slower |
| WEAK | an effect is plausible but not documented at global scale |
| Label | Rule |
|---|---|
| Reported | value as issued by its source, with year |
| Inferred | reasoned from cited evidence; never a measurement |
| Estimated | Nexus analytical value with stated method |
| Scenario | conditional on stated assumptions |
| Expert input | structured editorial judgement awaiting evidence |
A.2Model card, Fusion System Model v0
- Model ID
- MDL-XT14-FUSION · v0.1
- Purpose
- represent fusion and frontier energy as infrastructure coupled to energy, fuel supply, materials, finance, workforce and licensing
- Family
- graph-based system of systems
- Inputs
- the cited sources of this edition; no proprietary data
- Method
- expert-specified coupling strengths (STRONG · MODERATE · WEAK) from assessments and analogue events
- Validation
- none yet, first validation against federation evidence in 2027
- Uncertainty
- qualitative; strengths are hypotheses, not measurements
- Domain of validity
- global scale; not for asset-, site- or country-level use
- Reproducibility
- strength table and sources published in this edition
typed in v0
documented within one season
documented, buffered
plausible, undocumented
A.3The baseline evidence cut
Every Nexus edition is published from a frozen evidence cut. The global baseline cut is documentary: it pins the exact edition of every source cited. Federation cuts begin with the first national Foundry cuts in 2027.
- Cut ID
- DC-XTECH-FUSION-GLOBAL-2026-B0
- Type
- baseline documentary cut
- Resolution policy
- pinned · as of 30 September 2026
- Sources pinned
- 46 cited sources, each at the edition and access date in the references
- Model runs
- none at baseline, analytical values are stated with their method
- Digest
- computed at freeze and recorded in the publication record
- Supersedes
- nothing, first cut of the series
- Superseded by
- the 2027 fusion annual cut
Lineage
- 01
source edition
- 02
pinned citation
- 03
finding
- 04
page
- 05
publication record
| Element | Baseline 2026 | 2027 global annual |
|---|---|---|
| Sources | cited global publications, pinned by edition | national, regional and sector cuts through one graph |
| Analysis | stated methods and editorial estimates | typed analysis specifications |
| Models | Fusion System Model v0 specification | model runs with receipts |
| Findings | twelve baseline findings | findings re-bound to federation evidence |
| Review | five passes scheduled | five passes on the exact digest |
A.4Evidence age and coverage
A 2026 global edition rests on evidence observed in many different years. This page shows each time base, so that no single year label hides older evidence.
| Indicator | Observed | Released | Cadence | Next release |
|---|---|---|---|---|
| NIF record shot | 2025 | Apr 2025 | per event | refurbished shots |
| JET energy record | 2023 | Oct 2023 · Feb 2024 | one-off | ITER results |
| WEST and EAST durations | 2025 | Jan to Feb 2025 | per event | next campaigns |
| ITER baseline | 2026 | page read 2026-11-03 | periodic | next Council update |
| Industry survey | 2026 | Jul 2026 | annual | July 2027 |
| US regulator rule | 2026 | Feb 2026 | per rule | final rule |
| UK strategy | 2026 | Mar 2026 | periodic | EN-8 draft |
| Tritium supply analysis | 2018 | 2018 · 2025 commentary | one-off | new studies |
| System | Coverage | Thinnest dimension |
|---|---|---|
| Experiments | GOOD | power and gain on a plant basis |
| Fuel cycle | THIN | tritium and lithium-6 volumes |
| Governance | PARTIAL | final rules and national plans |
| Investment | PARTIAL | public funding totals |
| Energy | THIN | electricity delivered to a grid |
| Materials | THIN | component lifetimes |
| Skills | THIN | workforce numbers |
| Frontier energy beyond fusion | THIN | covered by other editions |
| Field | Source that would fill it | Blocker |
|---|---|---|
| Electricity delivered to a grid from fusion | plant operators and grid operators | no plant in operation in the sources read; company plans only2423 |
| Facility electricity per NIF shot or per WEST pulse | laboratory facility reports | not on the pages read; gain counts laser energy on target only5 |
| Global tritium inventory and start-up demand on a common basis | IAEA, national tritium programmes, peer-reviewed supply studies | one conference analysis and one commentary read; estimates differ2022 |
| Lithium-6 enrichment capacity and demand | enrichment operators, national laboratories | one company presentation read; a 2026 preprint seen in search only2133 |
| ITER cost of the 2024 baseline | ITER Council documents | not on the page read; a figure appears only in search summaries26 |
| SPARC first plasma date and status | Commonwealth Fusion Systems and its regulators | date reported in search summaries only; no primary page opened29 |
| Commonwealth Fusion Systems offtake terms with Google | company releases | seen in search summaries only; terms not disclosed27 |
| Helion Microsoft agreement terms | company releases | release page returned a block; figure taken from the company page read2824 |
| Fusion Industry Association 2026 report from the report itself | FIA report30 | report page returned an error; figures come from a news service10 |
| IAEA World Fusion Outlook 2025 from the report itself | IAEA publication31 | publication page returned a payment error; figures come from news9 |
| Status of the final US rule on fusion machines | Federal Register and NRC | proposed rule read; no final rule located at evidence close14 |
| Status of the EU fusion strategy | European Commission | call for evidence read; no strategy text located18 |
| Public funding totals by country | ministries, OECD, national audit offices | not consolidated; UK, Germany and China figures are on different bases151619 |
| Workforce size and fabrication capacity by country | national statistics, industry surveys | not retrieved; capability rung stays LISTED |
A.5Evidence cards, two anchor sources
Published on the annual report site of Lawrence Livermore National Laboratory for 2025. One facility. Role: binds INF-001 and the gain tiles. Coverage: laser-driven inertial confinement.
EVD-XT14-001
Record fusion yield and gain at the National Ignition Facility5
Conference paper of the UK Atomic Energy Authority, 2018. One-off. Role: binds MIN-006. Coverage: heavy-water reactors and scenarios to 2055.
EVD-XT14-002
Global supply of tritium for fusion R and D from heavy-water reactors20
| Dimension | EVD-XT14-001 | EVD-XT14-002 |
|---|---|---|
| Completeness | one facility; one shot series | scenarios to 2055 on 2018 data |
| Timeliness | annual report for 2025 | about eight years old |
| Revision | yearly reports | revised from an earlier work |
| Method transparency | yield and laser energy stated | scenario assumptions stated |
| External validation | laboratory report; journal papers for earlier shots | conference review |
Evidence cards to follow in 2027
A.6Publication acceptance record
Editorial self-check at evidence close. Every applicable item carries a disposition; the remaining items are review, approval and deposit.
| Group | Area | Items | Pass | N/A | Pending |
|---|---|---|---|---|---|
| D1 | Identity and scope | 8 | 8 | 0 | 0 |
| D2 | Source and data | 12 | 9 | 1 | 2 |
| D3 | Analysis and models | 12 | 3 | 8 | 1 |
| D4 | Findings and claims | 9 | 8 | 0 | 1 |
| D5 | Figures, tables, maps | 10 | 6 | 2 | 2 |
| D6 | Editorial and citations | 10 | 8 | 0 | 2 |
| D7 | Review and approval | 13 | 0 | 0 | 13 |
| D8 | Artefact and design | 12 | 7 | 0 | 5 |
| D9 | Registry and release | 9 | 0 | 0 | 9 |
Publication gate
- Conditions met
- 14 of 23 at evidence close
- Blocking problems
- none recorded
- Open conditions
- reviews, approval of the exact digest, deposit, registry pointer
Not applicable at baseline
- Model runs
- first runs in Q1 2027
- Maps
- plates in Q2 2027
- Waivers
- none
A.7Status words
| Status | What it means |
|---|---|
| Observed | Measured directly and published by the source. |
| Reported | Published statistics of an official or institutional source. |
| Declared | Stated by the body concerned; not independently measured. |
| Estimated | A Nexus estimate from cited evidence, with its method in Annex A. |
| Modelled | Produced by a stated model from cited inputs. |
| Inferred | Reasoned from cited evidence; not measured. |
| Forecast | A projection by the cited source. |
| Simulated | A simulation result under stated assumptions. |
| Scenario | A conditional statement under stated assumptions; never a prediction. |
| Expert input | Expert judgement, recorded with its basis. |
| Candidate | Proposed for a later edition; not yet evidence. |
| Evidence-quality levels (EQL 1 to 5) grade the source behind a value; they are not a score of the subject. | |
A.8How the edition is made, released and corrected
Every edition is built from a sealed evidence cut, reviewed under three keys, signed and deposited before any site shows it as published; corrections go to Nexus Standards as change proposals and feed the next cut.
| Step | What happens | Source |
|---|---|---|
| 01 Evidence arrives from the pillars | Foundry seals observations and indicator series, Universe hands over after-action and scenario findings, and contributions are screened at every gateway, including this site’s. | |
| 02 The cut is sealed | On the cut date the evidence is pinned under one identifier, so anyone can rebuild the edition from exactly what it was built on. | |
| 03 The edition is assembled | The edition is drafted from its template and content pack. Agents may draft; they never publish and never decide. | |
| 04 The keys turn | At the publisher of record the truth key comes first: every value is checked against its source or stated method before the meaning and capital keys turn. No edition moves on until every key has been turned by a named steward. | |
| 05 The gate opens | A named approver releases one exact digest of the edition; any change after this point is a new version, never a silent edit. | |
| 06 Signed and deposited | The PDF, the web edition and the data bundle are signed together with a manifest and an RO-Crate description, and deposited on Zenodo with a concept and a version DOI. | |
| 07 Published on its desk’s site | Only then does the edition show as published on its desk’s Reports site, and the Collection lists it as a part. | |
| 08 Corrections go to Standards | Method and correction findings go to Nexus Standards as change proposals; citations, corrections and new contributions feed the next evidence cut. |
A teaching model of the process, not a forecast and not a record of any run; dates and counts on this page come from the programme record. Sources: Reports governance at GCRI Canada (2026); Zenodo, repository of record for Reports deposits (2026).
Lifecycle, one state at a time: Draft, Computed, Evidence bound, Reviewed, Approved for release, Published, Corrected, Superseded. This edition is a draft.
A.9Glossary and abbreviations
| Term | Meaning |
|---|---|
| Baseline Edition | the inaugural annual edition that fixes the reference state for the series |
| WEFH+B | water, energy, food, health and biodiversity, the national nexus core |
| Coupling | a typed dependency through which one system transmits to another |
| Protection gap | the share of losses not covered by insurance |
| Capability ladder | LISTED → EXISTS → ADEQUATE → TESTED → DEMONSTRATED |
| EQL | evidence-quality level, 1–5 |
| Evidence cut | a frozen resolution of exact sources and versions |
| NNC · NLC · NWG | National Nexus Consortium · National Leadership Council · National Working Groups |
| Abbreviation | Expansion |
|---|---|
| CANDU | Canada Deuterium Uranium heavy-water reactor |
| D-T | deuterium-tritium |
| EAST | Experimental Advanced Superconducting Tokamak |
| FIA | Fusion Industry Association |
| IAEA | International Atomic Energy Agency |
| ITER | international fusion research project in France |
| JET | Joint European Torus |
| NIF | National Ignition Facility |
| NRC | US Nuclear Regulatory Commission |
| STEP | Spherical Tokamak for Energy Production |
| TBR | tritium breeding ratio |
| WEST | Tungsten Environment in Steady-state Tokamak |
A.10Technical annex
| Item | Annex | Contents | Status |
|---|---|---|---|
| A.1 | Indicator definitions | the global indicator set, with units and sources | IN THIS EDITION |
| A.2 | Coupling strengths | the twenty-cell matrix and its rationale | IN THIS EDITION |
| A.3 | Scenario specification | SCN-XT14-FUE-01 assumptions and signposts | IN THIS EDITION |
| A.4 | Capability placements | rung evidence for fifteen functions | IN THIS EDITION |
| A.5 | Model diagnostics | first runs and validation | 2027 |
| A.6 | Sensitivity analyses | influence of coupling strengths | 2027 |
| A.7 | Cluster notes | cards for the major fusion device and fuel-cycle clusters | 2027 |
| A.8 | Review statements | pass-by-pass review record | AT RELEASE |
A.1 · indicator definition: target gain
- Construct
- fusion energy produced divided by the laser energy delivered to the target
- Unit
- times
- Method
- yield and laser energy as reported by the laboratory for a single shot
- Source
- Lawrence Livermore National Laboratory annual report5
- Uncertainty
- no uncertainty is stated on the page read
- Known limits
- laser energy on target only; facility electricity is not included; one facility
Notes
Numbers are the edition’s reference numbers, so a note reads the same in every chapter. The full list, with every source and its licence, is in Annex C. Annex C, references
- 24Helion (ed.), Orion, the first fusion power plant (company page; Malaga, Washington; construction from 2025; initial operations stated for 2028; Microsoft agreement for 50 MW; a vendor announcement, weak evidence). Helion Energy, Everett. Observation year 2026. Accessed 2026-11-03.back
- 23Commonwealth Fusion Systems and Eni (eds.), Eni and CFS sign over USD 1 billion power purchase agreement (joint company release of 22 September 2025; 400 MW ARC plant in Chesterfield County, Virginia; grid connection in the early 2030s; a vendor announcement, weak evidence). Commonwealth Fusion Systems, Devens. Observation year 2025. Accessed 2026-11-03.back
- 5Lawrence Livermore National Laboratory (ed.), National Ignition Facility 2025 (annual report page; 8.6 MJ on 7 April 2025 from 2.08 MJ delivered, target gain 4.13; refurbishment and enhanced yield capability to 2.6 MJ). Lawrence Livermore National Laboratory, Livermore. Observation year 2025. Accessed 2026-11-03.back
- 20Coleman, M. and Kovari, M., Global supply of tritium for fusion R and D from heavy water reactors (conference paper, UK Atomic Energy Authority; abstract and introduction read from the PDF; 0 to 27.7 kg available in 2055 across scenarios; 7.4 kg for a demonstration reactor in 2055 in one case). UK Atomic Energy Authority, Abingdon. Observation year 2018. Accessed 2026-11-03.back
- 22Theiding, T., Tritium: a few kilograms can make or break nuclear fusion (policy blog post of 6 March 2025; about 25 kg of civilian tritium in 2024; a student fellow commentary, weak evidence). Kleinman Center for Energy Policy, University of Pennsylvania, Philadelphia. Observation year 2024. Accessed 2026-11-03.back
- 21Pearson, R.J., The availability and supply of critical natural resources for the realisation of a fusion pilot plant: fuels for fusion (presentation to the US Department of Energy fusion workshop, 1 to 3 June 2022; lithium-6 is 7.4% of natural lithium; blankets need 30 to 90%; supply effectively zero; a company presentation, weak evidence). Kyoto Fusioneering, London. Observation year 2022. Accessed 2026-11-03.back
- 33UNVERIFIED, not opened: Ward, P. and colleagues, Lithium enrichment threatens to curb fusion deployment, arXiv:2605.04707, 2026, taken from search-result summaries. arXiv, Ithaca. Observation year 2026. Accessed 2026-11-03.back
- 26UNVERIFIED, not opened: ITER Organization and press (eds.), ITER 2024 baseline additional cost of about EUR 5 billion, taken from search-result summaries. Observation year 2024. Accessed 2026-11-03.back
- 29UNVERIFIED, not opened: Commonwealth Fusion Systems (ed.), SPARC status, first plasma reported as a 2027 target, taken from search-result summaries and secondary pages. Commonwealth Fusion Systems, Devens. Observation year 2026. Accessed 2026-11-03.back
- 27UNVERIFIED, not opened: Commonwealth Fusion Systems (ed.), offtake agreement with Google for 200 MW from the Virginia ARC plant, June 2025, taken from search-result summaries. Commonwealth Fusion Systems, Devens. Observation year 2025. Accessed 2026-11-03.back
- 28UNVERIFIED, not opened: Helion (ed.), Helion secures land and begins building on the site of the first fusion power plant, release of 30 July 2025 (the release page returned a block) and the 2023 Microsoft agreement, taken from search-result summaries. Helion Energy, Everett. Observation year 2025. Accessed 2026-11-03.back
- 30UNVERIFIED, not opened: Fusion Industry Association (ed.), The Global Fusion Industry in 2026 (report page returned an error; figures read through a news service). Fusion Industry Association, Washington. Observation year 2026. Accessed 2026-11-03.back
- 10World Nuclear News (ed.), Fusion industry raised USD4.5 billion in past year, report says (14 July 2026; Fusion Industry Association 2026 survey: USD 4.48 billion in 12 months, USD 14.24 billion cumulative, 56 companies; an industry survey, weak evidence). World Nuclear Association, London. Observation year 2026. Accessed 2026-11-03.back
- 31UNVERIFIED, not opened: IAEA (ed.), World Fusion Outlook 2025 (publication page returned a payment error; figures read through news). International Atomic Energy Agency, Vienna. Observation year 2025. Accessed 2026-11-03.back
- 9World Nuclear News (ed.), Fusion entering implementation phase, says Grossi (report on the IAEA World Fusion Outlook 2025; more than 160 devices; private investment above USD 10 billion; October 2025). World Nuclear Association, London. Observation year 2025. Accessed 2026-11-03.back
- 14US Nuclear Regulatory Commission (ed.), Federal Register notice of 26 February 2026, proposed rule on regulatory framework for fusion machines (10 CFR part 30; comments due 27 May 2026; the first 100,000 of 168,363 characters were read). Office of the Federal Register, Washington. Observation year 2026. Accessed 2026-11-03.back
- 18European Commission (ed.), Commission launches call for evidence to support first-ever EU-wide fusion strategy (news item of 6 June 2025; call open to 1 July 2025; strategy then programmed for the end of 2025). Directorate-General for Energy, Brussels. Observation year 2025. Accessed 2026-11-03.back
- 15UK Department for Energy Security and Net Zero (ed.), A new energy revolution: the UK plan for delivering fusion energy (policy paper of 16 March 2026; over GBP 2.5 billion over five years; GBP 1.3 billion for STEP and UK Fusion Energy; the first 100,000 of 127,790 characters were read). UK Government, London. Observation year 2026. Accessed 2026-11-03.back
- 16Clean Energy Wire (ed.), German government pledges more than EUR 2 bln for nuclear fusion (news report of 2 October 2025; cabinet plan of 1 October 2025). Clean Energy Wire, Berlin. Observation year 2025. Accessed 2026-11-03.back
- 19American Nuclear Society (ed.), China launches fusion-focused company (news report of 30 July 2025; China Fusion Energy Co., 15 billion yuan registered capital, subsidiary of a state nuclear group; BEST tokamak in Hefei hoped for 2027). American Nuclear Society, La Grange Park. Observation year 2025. Accessed 2026-11-03.back
- 7ITER Organization (ed.), ITER in a few lines (project page; baseline reviewed by the ITER Council in November 2024; start of research operation 2034; deuterium-tritium operation 2039; Q of 10, 500 MW from 50 MW). ITER Organization, Saint-Paul-lez-Durance. Observation year 2026. Accessed 2026-11-03.back