Methodology
How the edition was made: methods, the model card, the evidence cut and its age, the acceptance record and the glossary.
Contents
- ·Edition home
- ·Executive summary
- 1Advanced nuclear is firm infrastructure and a delivery test
- 2Key findings
- 3Systems and sectors at baseline
- 4Risks and capability
- 5Fuel supply gap while first-of-a-kind units are delayed
- 6Readings from the other desks
- 7The 2027 agenda
- 8Systems in depth
- AMethodology
- A.1 Methods
- A.2 Model card, Advanced nuclear System Model v0
- A.3 The baseline evidence cut
- A.4 Evidence age and coverage
- A.5 Evidence cards, two anchor sources
- A.6 Publication acceptance record
- A.7 Status words
- A.8 How the edition is made, released and corrected
- A.9 Glossary and abbreviations
- A.10 Technical annex
- BData appendix
- CReferences and record
- ·Complete edition, for print
A.1Methods
The global baseline uses published values and four simple derivations. Each is shown in full so that any reader can reproduce it.
| No. | Derivation | Calculation | Result |
|---|---|---|---|
| (1) | Rosatom share of 2025 world enrichment capacity | 29.133 ÷ 68.076 | ≈ 42.8% |
| (2) | Ratio of Vogtle 3 and 4 cost estimate of May 2022 to the initial estimate | 30.34 ÷ 14 | ≈ 2.17 times |
| (3) | NRC review time for the Natrium permit against the initial schedule | 18 ÷ 27 | ≈ 0.67 |
| (4) | Average net capacity per operable reactor, 2025 | 405,667 ÷ 443 | ≈ 916 MWe |
| Strength | Definition |
|---|---|
| STRONG | a disruption in the source system has historically changed the target system’s service or output within one season, in more than one region |
| MODERATE | an effect is documented but buffered or slower |
| WEAK | an effect is plausible but not documented at global scale |
| Label | Rule |
|---|---|
| Reported | value as issued by its source, with year |
| Inferred | reasoned from cited evidence; never a measurement |
| Estimated | Nexus analytical value with stated method |
| Scenario | conditional on stated assumptions |
| Expert input | structured editorial judgement awaiting evidence |
A.2Model card, Advanced nuclear System Model v0
- Model ID
- MDL-XT15-FISSION · v0.1
- Purpose
- represent advanced nuclear fission as infrastructure coupled to energy, fuel supply and enrichment, siting and waste, finance, workforce and licensing
- Family
- graph-based system of systems
- Inputs
- the cited sources of this edition; no proprietary data
- Method
- expert-specified coupling strengths (STRONG · MODERATE · WEAK) from assessments and analogue events
- Validation
- none yet, first validation against federation evidence in 2027
- Uncertainty
- qualitative; strengths are hypotheses, not measurements
- Domain of validity
- global scale; not for asset-, site- or country-level use
- Reproducibility
- strength table and sources published in this edition
typed in v0
documented within one season
documented, buffered
plausible, undocumented
A.3The baseline evidence cut
Every Nexus edition is published from a frozen evidence cut. The global baseline cut is documentary: it pins the exact edition of every source cited. Federation cuts begin with the first national Foundry cuts in 2027.
- Cut ID
- DC-XTECH-FISSION-GLOBAL-2026-B0
- Type
- baseline documentary cut
- Resolution policy
- pinned · as of 30 September 2026
- Sources pinned
- 42 cited sources, each at the edition and access date in the references
- Model runs
- none at baseline, analytical values are stated with their method
- Digest
- computed at freeze and recorded in the publication record
- Supersedes
- nothing, first cut of the series
- Superseded by
- the 2027 advanced nuclear annual cut
Lineage
- 01
source edition
- 02
pinned citation
- 03
finding
- 04
page
- 05
publication record
| Element | Baseline 2026 | 2027 global annual |
|---|---|---|
| Sources | cited global publications, pinned by edition | national, regional and sector cuts through one graph |
| Analysis | stated methods and editorial estimates | typed analysis specifications |
| Models | Advanced nuclear System Model v0 specification | model runs with receipts |
| Findings | twelve baseline findings | findings re-bound to federation evidence |
| Review | five passes scheduled | five passes on the exact digest |
A.4Evidence age and coverage
A 2026 global edition rests on evidence observed in many different years. This page shows each time base, so that no single year label hides older evidence.
| Indicator | Observed | Released | Cadence | Next release |
|---|---|---|---|---|
| Fleet counts | 2025 | page read 2026-11-03 | continuous | next annual update |
| Pilot program criticality | 2026 | Jun to Jul 2026 | per event | remaining participants |
| Natrium permit | 2026 | Mar 2026 | one-off | operating licence |
| Part 53 rule | 2026 | Mar 2026 | one-off | first application |
| HALEU page | 2024 | Dec 2024 | periodic | new DOE update |
| Enrichment capacity | 2025 | fuel report 2025 | annual | next report |
| Reactor cost records | 2022 to 2026 | May 2022 to Feb 2026 | per event | new estimates |
| Waste volume study | 2022 | May 2022 | one-off | new studies |
| System | Coverage | Thinnest dimension |
|---|---|---|
| Reactors | PARTIAL | operating record of advanced units |
| Licensing | GOOD | review times outside the United States |
| Fuel | PARTIAL | HALEU output by year |
| Cost | PARTIAL | delivered cost of advanced units |
| Waste | THIN | common basis for comparison |
| Supply chain | THIN | fabrication capacity |
| Skills | THIN | workforce numbers |
| Climate role | THIN | life-cycle emissions |
| Field | Source that would fill it | Blocker |
|---|---|---|
| Delivered cost of first-of-a-kind advanced and small reactors | owners, national audit bodies, regulator filings | no advanced unit is complete; only modelled costs and large-unit records were read151725 |
| HALEU production against demand, by year | DOE, Centrus, national statistics | one DOE page read; output by year not found11 |
| World nuclear capacity projections for 2050 from the IAEA report | IAEA Energy, Electricity and Nuclear Power Estimates | the report page was not opened; figures appear only in trade summaries2 |
| Executive Order 14301 text on the test reactor goal | White House presidential actions | the page address returned not found; the goal comes from a society report56 |
| Operating record of any commercial advanced reactor | operators and regulators | none found operating at baseline |
| Linglong One commissioning and commercial operation | CNNC and national regulator releases | the profile page says commissioning is expected during 2026; no confirmation was found18 |
| Count of small reactor designs and projects | OECD NEA dashboard, IAEA booklet | the dashboard page returned a service error; the booklet was not opened2942 |
| Uranium resources and demand projections | OECD NEA and IAEA Red Book | the page returned forbidden30 |
| Life-cycle emissions of nuclear generation | UNECE, IPCC | both pages returned forbidden or could not be read3536 |
| Cooling-water and land use of new sites | site licence applications and environmental reports | not retrieved |
| Fabrication capacity and materials dependence by country | industry and trade statistics | not retrieved |
| Nuclear workforce size and skills gaps | national statistics, OECD, industry surveys | not retrieved; capability rung stays LISTED |
| Regulator pages for NuScale, Kairos and Darlington | NRC, CNSC, OPG | pages returned not found or forbidden; figures come from country profiles14313839 |
| Capability rungs beyond licensing and planning | agencies, operators, laboratories | not reviewed |
A.5Evidence cards, two anchor sources
Issued by the US Department of Energy in March 2026. One-off. Role: binds INF-003 and the licensing tile. Coverage: one sodium-cooled reactor at one site.
EVD-XT15-001
Natrium construction permit release8
Compiled by the World Nuclear Association from its 2025 fuel report. Annual. Role: binds TRD-007 and the supply tile. Coverage: operator capacity for 2022, 2025 and a 2030 projection.
EVD-XT15-002
Uranium enrichment capacity table12
| Dimension | EVD-XT15-001 | EVD-XT15-002 |
|---|---|---|
| Completeness | one reactor; scope of permit stated | four operators plus others; China estimated |
| Timeliness | issued within days of the permit | annual; 2025 data |
| Revision | no correction seen | annual updates |
| Method transparency | review process described by the agency | compiled data; China method stated |
| External validation | regulator decision | industry compilation |
Evidence cards to follow in 2027
A.6Publication acceptance record
Editorial self-check at evidence close. Every applicable item carries a disposition; the remaining items are review, approval and deposit.
| Group | Area | Items | Pass | N/A | Pending |
|---|---|---|---|---|---|
| D1 | Identity and scope | 8 | 8 | 0 | 0 |
| D2 | Source and data | 12 | 9 | 1 | 2 |
| D3 | Analysis and models | 12 | 3 | 8 | 1 |
| D4 | Findings and claims | 9 | 8 | 0 | 1 |
| D5 | Figures, tables, maps | 10 | 6 | 2 | 2 |
| D6 | Editorial and citations | 10 | 8 | 0 | 2 |
| D7 | Review and approval | 13 | 0 | 0 | 13 |
| D8 | Artefact and design | 12 | 7 | 0 | 5 |
| D9 | Registry and release | 9 | 0 | 0 | 9 |
Publication gate
- Conditions met
- 14 of 23 at evidence close
- Blocking problems
- none recorded
- Open conditions
- reviews, approval of the exact digest, deposit, registry pointer
Not applicable at baseline
- Model runs
- first runs in Q1 2027
- Maps
- plates in Q2 2027
- Waivers
- none
A.7Status words
| Status | What it means |
|---|---|
| Observed | Measured directly and published by the source. |
| Reported | Published statistics of an official or institutional source. |
| Declared | Stated by the body concerned; not independently measured. |
| Estimated | A Nexus estimate from cited evidence, with its method in Annex A. |
| Modelled | Produced by a stated model from cited inputs. |
| Inferred | Reasoned from cited evidence; not measured. |
| Forecast | A projection by the cited source. |
| Simulated | A simulation result under stated assumptions. |
| Scenario | A conditional statement under stated assumptions; never a prediction. |
| Expert input | Expert judgement, recorded with its basis. |
| Candidate | Proposed for a later edition; not yet evidence. |
| Evidence-quality levels (EQL 1 to 5) grade the source behind a value; they are not a score of the subject. | |
A.8How the edition is made, released and corrected
Every edition is built from a sealed evidence cut, reviewed under three keys, signed and deposited before any site shows it as published; corrections go to Nexus Standards as change proposals and feed the next cut.
| Step | What happens | Source |
|---|---|---|
| 01 Evidence arrives from the pillars | Foundry seals observations and indicator series, Universe hands over after-action and scenario findings, and contributions are screened at every gateway, including this site’s. | |
| 02 The cut is sealed | On the cut date the evidence is pinned under one identifier, so anyone can rebuild the edition from exactly what it was built on. | |
| 03 The edition is assembled | The edition is drafted from its template and content pack. Agents may draft; they never publish and never decide. | |
| 04 The keys turn | At the publisher of record the truth key comes first: every value is checked against its source or stated method before the meaning and capital keys turn. No edition moves on until every key has been turned by a named steward. | |
| 05 The gate opens | A named approver releases one exact digest of the edition; any change after this point is a new version, never a silent edit. | |
| 06 Signed and deposited | The PDF, the web edition and the data bundle are signed together with a manifest and an RO-Crate description, and deposited on Zenodo with a concept and a version DOI. | |
| 07 Published on its desk’s site | Only then does the edition show as published on its desk’s Reports site, and the Collection lists it as a part. | |
| 08 Corrections go to Standards | Method and correction findings go to Nexus Standards as change proposals; citations, corrections and new contributions feed the next evidence cut. |
A teaching model of the process, not a forecast and not a record of any run; dates and counts on this page come from the programme record. Sources: Reports governance at GCRI Canada (2026); Zenodo, repository of record for Reports deposits (2026).
Lifecycle, one state at a time: Draft, Computed, Evidence bound, Reviewed, Approved for release, Published, Corrected, Superseded. This edition is a draft.
A.9Glossary and abbreviations
| Term | Meaning |
|---|---|
| Baseline Edition | the inaugural annual edition that fixes the reference state for the series |
| WEFH+B | water, energy, food, health and biodiversity, the national nexus core |
| Coupling | a typed dependency through which one system transmits to another |
| Protection gap | the share of losses not covered by insurance |
| Capability ladder | LISTED → EXISTS → ADEQUATE → TESTED → DEMONSTRATED |
| EQL | evidence-quality level, 1–5 |
| Evidence cut | a frozen resolution of exact sources and versions |
| NNC · NLC · NWG | National Nexus Consortium · National Leadership Council · National Working Groups |
| Abbreviation | Expansion |
|---|---|
| CFR | Code of Federal Regulations |
| DOE | US Department of Energy |
| EO | executive order |
| HALEU | high-assay low-enriched uranium |
| HTR-PM | high-temperature gas-cooled reactor pebble-bed module |
| IAEA | International Atomic Energy Agency |
| LEU | low-enriched uranium |
| MWe | megawatts of electrical output |
| NRC | US Nuclear Regulatory Commission |
| SMR | small modular reactor |
| SWU | separative work unit |
| STUK | Finnish radiation and nuclear safety authority |
A.10Technical annex
| Item | Annex | Contents | Status |
|---|---|---|---|
| A.1 | Indicator definitions | the global indicator set, with units and sources | IN THIS EDITION |
| A.2 | Coupling strengths | the twenty-cell matrix and its rationale | IN THIS EDITION |
| A.3 | Scenario specification | SCN-XT15-FUE-01 assumptions and signposts | IN THIS EDITION |
| A.4 | Capability placements | rung evidence for fifteen functions | IN THIS EDITION |
| A.5 | Model diagnostics | first runs and validation | 2027 |
| A.6 | Sensitivity analyses | influence of coupling strengths | 2027 |
| A.7 | Cluster notes | cards for the major reactor and fuel supply clusters | 2027 |
| A.8 | Review statements | pass-by-pass review record | AT RELEASE |
A.1 · indicator definition: enrichment capacity
- Construct
- annual separative work capacity of uranium enrichment plants, by operator
- Unit
- million separative work units (SWU) a year
- Method
- operator capacity as compiled in a 2025 industry fuel report and shown on the page
- Source
- World Nuclear Association enrichment page12
- Uncertainty
- China values are estimates that assume enough capacity is built for its domestic fleet
- Known limits
- capacity is not output; shares are derived by the editors, method (1)
Notes
Numbers are the edition’s reference numbers, so a note reads the same in every chapter. The full list, with every source and its licence, is in Annex C. Annex C, references
- 15World Nuclear Association (ed.), Nuclear Power in the USA (country profile; 94 operable reactors, 96,952 MWe; Vogtle 3 and 4 cost estimates; Kemmerer permit March 2026; Clinch River construction licence September 2026; Palisades and Crane restart status; page states three reactors critical by July 2026). World Nuclear Association, London. Observation year 2026. Accessed 2026-11-03.back
- 17World Nuclear Association (ed.), Nuclear Power in the United Kingdom (country profile, first 100,000 characters read; Rolls-Royce SMR delivery contract April 2026 for three Wylfa units with up to GBP 599 million loan financing; Hinkley Point C GBP 35 billion in 2015 prices, February 2026; Sizewell C). World Nuclear Association, London. Observation year 2026. Accessed 2026-11-03.back
- 25Steigerwald, B., Weibezahn, J., Slowik, M. and von Hirschhausen, C., Uncertainties in estimating production costs of future nuclear technologies: a model-based analysis of small modular reactors, Energy 281, 128204, 2023 (abstract page read). Elsevier, Amsterdam. Observation year 2023. Accessed 2026-11-03.back
- 11US Department of Energy, Office of Nuclear Energy (ed.), What is high-assay low-enriched uranium (HALEU)? (article of 3 December 2024; enrichment 5% to less than 20% U-235; demand could reach 50 metric tons a year by 2035; Piketon more than 100 kg enriched). US Department of Energy, Washington. Observation year 2024. Accessed 2026-11-03.back
- 2UNVERIFIED, not opened: IAEA (ed.), Energy, Electricity and Nuclear Power Estimates for the Period up to 2050, 2025 edition (377 GW at end of 2024; high case 992 GW and low case 561 GW in 2050), taken from search-result summaries of trade reports; the IAEA page was not retrieved. International Atomic Energy Agency, Vienna. Observation year 2025. Accessed 2026-11-03.back
- 5UNVERIFIED, not opened: The White House (ed.), Reforming Nuclear Reactor Testing at the Department of Energy, Executive Order 14301, 23 May 2025, the page address returned not found; the goal of three reactors achieving criticality by 4 July 2026 is taken from the American Nuclear Society report. The White House, Washington. Observation year 2025. Accessed 2026-11-03.back
- 6American Nuclear Society (ed.), The deadline arrives: checking in on the Reactor Pilot Program (news article, 2 July 2026; criticality by Antares 4 June, Valar 18 June, Deployable Energy 1 July; ten companies selected in August 2025; status of the remaining participants). American Nuclear Society, La Grange Park. Observation year 2026. Accessed 2026-11-03.back
- 18World Nuclear Association (ed.), Nuclear Power in China (country profile, first 100,000 characters read; 65 reactors, 65,085 MWe operable; 39 under construction; HTR-PM commercial operation December 2023; Linglong One commissioning expected during 2026; 110 GWe target by 2030). World Nuclear Association, London. Observation year 2026. Accessed 2026-11-03.back
- 29UNVERIFIED, not opened: OECD Nuclear Energy Agency (ed.), The NEA Small Modular Reactor Dashboard, second edition, the page returned a service error; no figure from it is used. OECD NEA, Paris. Observation year 2024. Accessed 2026-11-03.back
- 42UNVERIFIED, not opened: IAEA (ed.), Advances in Small Modular Reactor Technology Developments, 2022 edition, cited from memory without a figure. International Atomic Energy Agency, Vienna. Observation year 2022. Accessed 2026-11-03.back
- 30UNVERIFIED, not opened: OECD NEA and IAEA (eds.), Uranium 2024: Resources, Production and Demand, the page returned forbidden; no figure from it is used. OECD NEA, Paris. Observation year 2025. Accessed 2026-11-03.back
- 35UNVERIFIED, not opened: UNECE (ed.), Life Cycle Assessment of Electricity Generation Options, 2021, the page returned forbidden; no figure from it is used. United Nations Economic Commission for Europe, Geneva. Observation year 2021. Accessed 2026-11-03.back
- 36UNVERIFIED, not opened: IPCC (ed.), Climate Change 2022: Mitigation of Climate Change, Working Group III, chapter 6, the page returned forbidden; no figure from it is used. Intergovernmental Panel on Climate Change, Geneva. Observation year 2022. Accessed 2026-11-03.back
- 14World Nuclear Association (ed.), Nuclear Power in Canada (country profile; Darlington BWRX-300, construction licence April 2025, first nuclear concrete 26 June 2026, operation expected 2030, CAD 20.9 billion for four units; page lists 316 MWe gross and describes 300 MWe). World Nuclear Association, London. Observation year 2026. Accessed 2026-11-03.back
- 31UNVERIFIED, not opened: US Nuclear Regulatory Commission (ed.), NuScale US460 standard design approval page, the page address returned not found; the approval is cited from memory without a figure. US NRC, Rockville. Observation year 2025. Accessed 2026-11-03.back
- 38UNVERIFIED, not opened: US Nuclear Regulatory Commission (ed.), Kairos Power Hermes test reactor licensing page, the page address returned not found; no figure from it is used. US NRC, Rockville. Observation year 2025. Accessed 2026-11-03.back
- 39UNVERIFIED, not opened: Ontario Power Generation (ed.), Darlington New Nuclear Project page, the page returned forbidden; Darlington figures are taken from the World Nuclear Association country profile. OPG, Toronto. Observation year 2026. Accessed 2026-11-03.back
- 8US Department of Energy, Office of Nuclear Energy (ed.), NRC Issues Construction Permit for TerraPower’s Natrium Advanced Reactor (article, 9 March 2026; 345 MWe sodium-cooled fast reactor, storage lifts output to 500 MW; Kemmerer Unit 1, Wyoming; operating licence separate). US Department of Energy, Washington. Observation year 2026. Accessed 2026-11-03.back
- 12World Nuclear Association (ed.), Uranium Enrichment (information library page; capacity table from the WNA Nuclear Fuel Report 2025: 68.076 million SWU in 2025, Rosatom 29.133, Urenco 17.300, CNNC 13.789 estimated, Orano 7.500; US ban on Russian low-enriched uranium from August 2024). World Nuclear Association, London. Observation year 2025. Accessed 2026-11-03.back
- 10US Nuclear Regulatory Commission (ed.), 10 CFR Part 53 rulemaking page (final rule 91 FR 15696; risk-informed, performance-based, technology-inclusive framework; background in NEIMA and the ADVANCE Act). US Nuclear Regulatory Commission, Rockville. Observation year 2026. Accessed 2026-11-03.back