Global Energy Risk and Resilience Report 2026: Baseline Edition, The State of the World’s Energy System.
Global Sector Risk and Resilience
Global Energy 2026
Imprint
- Editor
- Saeed Valadbaygi, Chief Steward and Managing Editor, the Global Centre for Risk and Innovation (GCRI)
- Publisher of record
- The Global Centre for Risk and Innovation (GCRI) for the Nexus Consortium, Toronto
- Report number
- NR-SECTOR-ENERGY-GLOBAL-2026-BASELINE
- Evidence close
- 30 September 2026, cut DC-SECTOR-ENERGY-GLOBAL-2026-B0
- Status
- Draft under stewardship review; not yet released
- DOI and UNI
- Issued at deposit
- Licence
- CC BY 4.0 for Nexus-authored text, tables and figures; third-party material keeps its own licence
- Cite as
- Valadbaygi, S. (Ed.). (2026). Global Energy Risk and Resilience Report 2026: Baseline Edition, The State of the World’s Energy System. (Baseline Edition 2026, Report No. NR-SECTOR-ENERGY-GLOBAL-2026-BASELINE) [Draft under review]. The Global Centre for Risk and Innovation (GCRI). https://therisk.global/nexus-reports/editions/gs-02/
Contents
- Global Energy 2026
- Executive summary
Executive summary
The edition on a few pages: the abstract, the key messages, the headline finding and what each steward reads in it.
S.1Abstract
The world enters 2027 with an energy system that is growing, electrifying and under strain at the same time. Global energy demand grew 1.3% in 2025 and electricity demand grew nearly 3%, more than twice as fast2. Solar supplied more than a quarter of the growth in energy demand, and renewables (33.8%) edged ahead of coal (33.0%) in global electricity generation for the first time27. Energy-related CO2 emissions still reached a record of more than 38 Gt2. Investment is estimated at USD 3.4 trillion in 2026, with about USD 1.6 trillion in electricity supply and infrastructure1. Access is unfinished: 655 million people lacked electricity in 2024 and about 2.0 billion relied mainly on polluting fuels for cooking8. Security of supply is the sharpest pressure. The Middle East conflict that began on 28 February 2026 cut flows through the Strait of Hormuz, IEA members made a record emergency oil release, and EIA assumes flows stay constrained through the fourth quarter of 2026471112. Critical minerals add a second chokepoint: refining is concentrated and export controls have spread3. Data centres are a fast-growing load, about 415 TWh in 2024 and about 945 TWh by 2030 in the IEA base case4. This baseline sets out what the evidence supports and where it is thin. It ranks no country and recommends no policy.
S.2Key messages
Six readings that frame the energy baseline, and the eight questions this edition answers, each with its status and source.
Energy demand grew 1.3% in 2025 and electricity nearly 3%.2
How fast is energy demand growing?Reported
Solar led growth; renewables edged past coal in generation.27
What is changing in supply?Reported
No. Energy CO2 reached a record above 38 Gt, up about 0.4%.2
Are emissions falling?Reported
About USD 3.4 trillion in 2026, with electricity supply and infrastructure at USD 1.6 trillion.1
Where is the money going?Reported
655 million without electricity and about 2.0 billion cooking with polluting fuels.8
Who still lacks energy?Reported
Hormuz flows were cut from March 2026 and remain constrained in the EIA outlook.4711
How secure is fuel supply?Reported
Refining is concentrated and export controls have tripled in scope.3
Do minerals add risk?Reported
A fuel shock that coincides with heat and grid stress. SCN-GS02-LNG-01
What will 2027 test first?Expert input
S.3Headline finding
ReportedEQL 5NRF-SECTOR-ENERGY-GLOBAL-2026-BASELINE-HLT-007
In 2024, 655 million people lacked electricity and about 2.0 billion people relied mainly on polluting fuels for cooking.
| Item | Bar, scaled to the largest value | Value |
|---|---|---|
| Without electricity | 655 | |
| Relying on polluting cooking fuels | 2,000 |
Source: SDG 7 custodian agencies, Extended Report 20268.
The access gap is now concentrated in Sub-Saharan Africa, which holds 563 million of the people without electricity and 970 million of those without clean cooking. Affordability is a binding constraint: only about 22% of households without access can afford the monthly payments for a basic solar home system8.
S.4At a glance
S.5What each steward reads in it
GCRI · KEY T
Technical Truth
The evidence supports reading energy as the coupling layer of the WEFH+B system.
GRF · KEY M
Public Meaning
For most people energy risk arrives as a power cut, a higher bill or a cooking fire.
GRA · KEY F
Capital Meaning
Readiness implications only. Investment is high, price volatility has risen and public finance for minerals is growing.
NEXUS
Synthesis
The energy system is well measured at the level of demand and generation and thinly measured at the level of equipment, constraints and water.
S.6What this edition is, and is not
What this edition is
A baseline: the 2026 state of the world’s energy system and the couplings through which it carries risk into other systems. It synthesises published evidence and ranks no country, company or asset.
What it is not
Not an energy-security ranking, a forecast of prices, a supply recommendation or an assessment of any utility, regulator, producer or government. Energy policy, markets and operations rest with national authorities, system operators and companies.
What comes next
National, regional and sector evidence feeds the 2027 energy edition through the federation. Each edition reports what changed against this baseline: observations, source revisions, method changes, scenario updates and corrections.
Notes
Numbers are the edition’s reference numbers, so a note reads the same in every chapter. The full list, with every source and its licence, is in Annex C. Annex C, references
- 2IEA (ed.), Global Energy Review 2026 (revised version, May 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 7Ember (ed.), Global Electricity Review 2026: 2025 in review (generation, demand, solar, coal). Ember, London. Observation year 2025. Accessed 2026-11-03.back
- 1IEA (ed.), World Energy Investment 2026, launch presentation, Paris, 28 May 2026. International Energy Agency, Paris. Observation year 2026 (estimates, with 2025 data). Accessed 2026-11-03.back
- 8UN DESA Statistics Division (ed.), The Sustainable Development Goals Extended Report 2026, Goal 7 indicator storylines (inputs as of 30 April 2026). United Nations, New York. Observation year 2024. Accessed 2026-11-03.back
- 47US Energy Information Administration (ed.), Short-Term Energy Outlook, September 2026 (Brent about USD 91 a barrel in the fourth quarter of 2026; Middle East oil flows assumed constrained through the fourth quarter of 2026). EIA, Washington. Observation year 2026. Accessed 2026-11-03.back
- 11UNVERIFIED, not opened: IEA (ed.), Oil Market Report, September 2026; flows through the strait of 7.6 mb/d in August, 2026 supply 100.7 mb/d and demand 102.5 mb/d, and taken from search-result summaries. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 12UNVERIFIED, not opened: IEA (ed.), collective action on emergency oil stocks agreed on 11 March 2026 (400 million barrels, the largest release in the agency’s history), with export volumes through the strait below 10% of pre-conflict levels and pre-war flows of about 20 mb/d, taken from search-result summaries; the release itself is also noted in the opened minerals outlook [3]. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 3IEA (ed.), Global Critical Minerals Outlook 2026 (revised version, July 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 4IEA (ed.), Energy and AI (World Energy Outlook Special Report). International Energy Agency, Paris, April 2025. Observation year 2024. Accessed 2026-11-03.back
- Global Energy 2026
- Chapter 1
Energy is where the systems meet
Part I describes systems and their couplings. It ranks no country or operator and assesses no authority.
1.1The questions this part answers
Key questions
- Where is energy risk concentrated?
- Which couplings carry energy shocks into other systems?
- Which energy capabilities hold under compound stress?
- What must 2027 evidence measure first?
In this part
- Narrative
- Headline finding
- Lead figure
- Five coupling chapters
- Twelve-domain reading
- Sector screens
- Dependency matrix
- Risk objects
- Capability ladder
- Scenario
- Three lenses
- Portfolio
1.2The argument
Energy is usually reported as a sector: fuels, power, prices. The 2026 evidence reads it as the medium through which almost every other system’s risk travels. Water pumping and cooling, fertiliser and cold chains, clinics and cooking, and the digital economy all rest on it834.
The supply side is changing at the margin. Solar was the largest source of growth in energy demand in 2025, and renewables edged past coal in global generation27. Yet fossil fuels still supplied about 86% of primary energy15, and energy-related CO2 reached a record above 38 Gt2.
Security is the sharpest pressure. After the conflict began on 28 February 2026, flows through the Strait of Hormuz fell sharply, IEA members made a record emergency oil release and EIA assumes flows stay constrained through the fourth quarter471112. The same shock reached LNG, aluminium and sulphur markets313.
Electricity is the common thread. It grew more than twice as fast as energy demand in 20252, data centres are an increasing share of it4, and the grids that carry it fail in ways that are only now understood, as the Iberian blackout shows9. Access remains unfinished for 655 million people8.
The cooking gap is about three times the electricity gap. Both are concentrated in the same places, so they compound each other’s effects on health and time use8.
| Item | Bar, scaled to the largest value | Value |
|---|---|---|
| Polluting cooking fuels | 2000 | |
| Without electricity | 655 |
Source: as cited in the note to this figure. Year 2024.
Figure ID FIG-SECTOR-ENERGY-GLOBAL-2026-BASELINE-01-003
1.3Twenty couplings between five systems
The energy-centred matrix types the twenty couplings between the five core systems, read for their energy content. Strengths are Nexus estimates (ESTIMATED) from the cited evidence and analogue events; they set the graph that 2027 evidence will test.
Each line is one coupling from one system to another, drawn by the strength the edition assigns. Strengths are Nexus estimates from the cited evidence and analogue events.
- Strong
- Moderate
- Weak
Source: this edition’s coupling matrix (Table 1.1); status Estimated.
| From, to | WAT | ENE | FOO | HLT | BIO |
|---|---|---|---|---|---|
| WAT Water | · | STRONG hydro · cooling water | MODERATE irrigation pumping load | WEAK supply and treatment | MODERATE reservoir flows |
| ENE Energy | STRONG pumping · treatment · desalination | · | STRONG fuel · fertiliser · cold chain | STRONG clean cooking · clinics · cooling | MODERATE mining · land use |
| FOO Food | WEAK withdrawals | MODERATE bioenergy · diesel pumping | · | WEAK nutrition | MODERATE land for biofuel |
| HLT Health | WEAK workforce | WEAK workforce | WEAK labour | · | WEAK residues |
| BIO Biodiversity | MODERATE catchments | MODERATE biomass · hydrology | WEAK pollination | WEAK zoonoses | · |
| Strength: strong, moderate or weak; a Nexus estimate (status Estimated) from cited evidence and analogue events. The scale is defined in Annex A. | |||||
Transmission paths
- 01
CLI → ENE → HLT
A heat wave raises cooling demand while supply is short; clinics and homes lose power.
- 02
ENE → FOO
Fuel, fertiliser and acid price shocks reach farms and food prices.
Reported 2026 sulphur and fertiliser disruption3
- 03
MIN → ENE
Export controls on minerals slow power equipment and batteries.
Reported 2025 rare-earth and graphite controls3
- 04
TRD → ENE → FIN
A chokepoint closure lifts prices and strains importers’ budgets.
- 05
AIC → ENE
Clustered data-centre load tightens local grids.
1.4Reinforcing loops
A shock entering either system of a loop can return amplified through the other.
| Loop | First direction | Second direction |
|---|---|---|
| WAT and ENE | Water to energy: hydro · cooling water | Energy to water: pumping · treatment · desalination |
| A causal-loop reading of the matrix (Sterman, Business Dynamics, 2000): structural, from estimated strengths, not a measured feedback. | ||
Notes
Numbers are the edition’s reference numbers, so a note reads the same in every chapter. The full list, with every source and its licence, is in Annex C. Annex C, references
- 8UN DESA Statistics Division (ed.), The Sustainable Development Goals Extended Report 2026, Goal 7 indicator storylines (inputs as of 30 April 2026). United Nations, New York. Observation year 2024. Accessed 2026-11-03.back
- 3IEA (ed.), Global Critical Minerals Outlook 2026 (revised version, July 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 4IEA (ed.), Energy and AI (World Energy Outlook Special Report). International Energy Agency, Paris, April 2025. Observation year 2024. Accessed 2026-11-03.back
- 2IEA (ed.), Global Energy Review 2026 (revised version, May 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 7Ember (ed.), Global Electricity Review 2026: 2025 in review (generation, demand, solar, coal). Ember, London. Observation year 2025. Accessed 2026-11-03.back
- 15UNVERIFIED, not opened: Energy Institute (ed.), Statistical Review of World Energy 2026 (75th edition; fossil fuels about 86% of primary energy, hydropower 2.7%, electricity demand up 3%); values taken from a trade-press summary that was opened, not from the Review. Energy Institute, London. Observation year 2025. Accessed 2026-11-03.back
- 47US Energy Information Administration (ed.), Short-Term Energy Outlook, September 2026 (Brent about USD 91 a barrel in the fourth quarter of 2026; Middle East oil flows assumed constrained through the fourth quarter of 2026). EIA, Washington. Observation year 2026. Accessed 2026-11-03.back
- 11UNVERIFIED, not opened: IEA (ed.), Oil Market Report, September 2026; flows through the strait of 7.6 mb/d in August, 2026 supply 100.7 mb/d and demand 102.5 mb/d, and taken from search-result summaries. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 12UNVERIFIED, not opened: IEA (ed.), collective action on emergency oil stocks agreed on 11 March 2026 (400 million barrels, the largest release in the agency’s history), with export volumes through the strait below 10% of pre-conflict levels and pre-war flows of about 20 mb/d, taken from search-result summaries; the release itself is also noted in the opened minerals outlook [3]. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 13UNVERIFIED, not opened: IEA (ed.), Gas Market Report, Q2-2026; Ras Laffan offline since early March 2026 and nearly a fifth of global LNG supply removed, taken from search-result summaries. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 9ENTSO-E (ed.), 28 April 2025 Iberian blackout: final report of the expert panel (publication page; report dated 20 March 2026). ENTSO-E, Brussels. Observation year 2025. Accessed 2026-11-03.back
- Global Energy 2026
- Chapter 2
Key findings
Twelve findings carry the energy baseline. They are grouped by coupling and never ranked. Each resolves to its source or, where Nexus analysis is involved, to its stated method.
2.1Headline finding
ReportedEQL 5NRF-SECTOR-ENERGY-GLOBAL-2026-BASELINE-HLT-007
In 2024, 655 million people lacked electricity and about 2.0 billion people relied mainly on polluting fuels for cooking.
| Item | Bar, scaled to the largest value | Value |
|---|---|---|
| Without electricity | 655 | |
| Relying on polluting cooking fuels | 2,000 |
Source: SDG 7 custodian agencies, Extended Report 20268.
Implication
The access gap is now concentrated in Sub-Saharan Africa, which holds 563 million of the people without electricity and 970 million of those without clean cooking. Affordability is a binding constraint: only about 22% of households without access can afford the monthly payments for a basic solar home system8.
What would move it
The next SDG 7 report, the pace of Mission 300 connections and the affordability of off-grid solar would each move this finding.
2.2Energy
ReportedEQL 5NRF-SECTOR-ENERGY-GLOBAL-2026-BASELINE-ENE-001
Global energy demand grew 1.3% (8 EJ) in 2025, down from 2% in 2024, and electricity demand grew nearly 3%, more than twice as fast.215
ReportedEQL 4NRF-SECTOR-ENERGY-GLOBAL-2026-BASELINE-ENE-002
Solar PV met more than 25% of the growth in global energy demand in 2025, and low-emissions sources together met nearly 60%.2
ReportedEQL 4NRF-SECTOR-ENERGY-GLOBAL-2026-BASELINE-ENE-003
Renewables supplied 33.8% of global electricity in 2025 and coal 33.0%; fossil generation fell 38 TWh, the first annual fall since 2020.7
ReportedEQL 3NRF-SECTOR-ENERGY-GLOBAL-2026-BASELINE-ENE-009
Qatar’s Ras Laffan LNG complex has been offline since early March 2026, removing nearly a fifth of global LNG supply, after a build-out of about 300 bcm a year of new LNG capacity was expected by 2030.513
2.3Climate forcing
ReportedEQL 4NRF-SECTOR-ENERGY-GLOBAL-2026-BASELINE-CLI-004
Energy-related CO2 emissions rose about 0.4% in 2025 to a record of more than 38 Gt.215
2.4Finance
ReportedEQL 4NRF-SECTOR-ENERGY-GLOBAL-2026-BASELINE-FIN-005
Global energy investment is estimated at USD 3.4 trillion in 2026, against USD 2.6 trillion in 2015, with electricity supply and infrastructure at about USD 1.6 trillion.117
2.5AIC
ReportedEQL 4NRF-SECTOR-ENERGY-GLOBAL-2026-BASELINE-AIC-006
Data centres used about 415 TWh in 2024, about 1.5% of global electricity, and the IEA base case reaches about 945 TWh by 2030.42
2.6Health
ReportedEQL 5NRF-SECTOR-ENERGY-GLOBAL-2026-BASELINE-HLT-007
655 million people lacked electricity in 2024 and about 2.0 billion relied mainly on polluting fuels for cooking.8
2.7Governance
ReportedEQL 4NRF-SECTOR-ENERGY-GLOBAL-2026-BASELINE-GOV-008
Oil flows through the Strait of Hormuz fell sharply after 28 February 2026; IEA members released a record 400 million barrels, and EIA assumes flows stay constrained through the fourth quarter of 2026.471112
2.8Minerals
ReportedEQL 4NRF-SECTOR-ENERGY-GLOBAL-2026-BASELINE-MIN-010
The top refining country’s average share of key energy minerals rose to 72% in 2025 from 70% in 2023, excluding rare earths, and the mineral tariff codes under Chinese export controls tripled since 2023.3
2.9Infrastructure
ReportedEQL 4NRF-SECTOR-ENERGY-GLOBAL-2026-BASELINE-INF-011
The Iberian blackout of 28 April 2025 came from interacting factors, including voltage control gaps, oscillations and generator disconnections, according to the ENTSO-E final report of 20 March 2026.9
2.10Systemic
Expert inputEQL 2NRF-SECTOR-ENERGY-GLOBAL-2026-BASELINE-SYS-012
The leading compound pathway for 2027 testing is a fuel supply shock that coincides with a hot, high-demand season and a stressed grid. § scenario
Notes
Numbers are the edition’s reference numbers, so a note reads the same in every chapter. The full list, with every source and its licence, is in Annex C. Annex C, references
- 8UN DESA Statistics Division (ed.), The Sustainable Development Goals Extended Report 2026, Goal 7 indicator storylines (inputs as of 30 April 2026). United Nations, New York. Observation year 2024. Accessed 2026-11-03.back
- 2IEA (ed.), Global Energy Review 2026 (revised version, May 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 15UNVERIFIED, not opened: Energy Institute (ed.), Statistical Review of World Energy 2026 (75th edition; fossil fuels about 86% of primary energy, hydropower 2.7%, electricity demand up 3%); values taken from a trade-press summary that was opened, not from the Review. Energy Institute, London. Observation year 2025. Accessed 2026-11-03.back
- 7Ember (ed.), Global Electricity Review 2026: 2025 in review (generation, demand, solar, coal). Ember, London. Observation year 2025. Accessed 2026-11-03.back
- 5IEA (ed.), Gas 2025: Analysis and forecasts to 2030 (Gas Market Report, Q4-2025). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 13UNVERIFIED, not opened: IEA (ed.), Gas Market Report, Q2-2026; Ras Laffan offline since early March 2026 and nearly a fifth of global LNG supply removed, taken from search-result summaries. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 1IEA (ed.), World Energy Investment 2026, launch presentation, Paris, 28 May 2026. International Energy Agency, Paris. Observation year 2026 (estimates, with 2025 data). Accessed 2026-11-03.back
- 17UNVERIFIED, not opened: IEA (ed.), World Energy Investment 2026, full report (clean energy about USD 2.2 trillion and fossil fuels about USD 1.2 trillion in search summaries). International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 4IEA (ed.), Energy and AI (World Energy Outlook Special Report). International Energy Agency, Paris, April 2025. Observation year 2024. Accessed 2026-11-03.back
- 47US Energy Information Administration (ed.), Short-Term Energy Outlook, September 2026 (Brent about USD 91 a barrel in the fourth quarter of 2026; Middle East oil flows assumed constrained through the fourth quarter of 2026). EIA, Washington. Observation year 2026. Accessed 2026-11-03.back
- 11UNVERIFIED, not opened: IEA (ed.), Oil Market Report, September 2026; flows through the strait of 7.6 mb/d in August, 2026 supply 100.7 mb/d and demand 102.5 mb/d, and taken from search-result summaries. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 12UNVERIFIED, not opened: IEA (ed.), collective action on emergency oil stocks agreed on 11 March 2026 (400 million barrels, the largest release in the agency’s history), with export volumes through the strait below 10% of pre-conflict levels and pre-war flows of about 20 mb/d, taken from search-result summaries; the release itself is also noted in the opened minerals outlook [3]. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 3IEA (ed.), Global Critical Minerals Outlook 2026 (revised version, July 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 9ENTSO-E (ed.), 28 April 2025 Iberian blackout: final report of the expert panel (publication page; report dated 20 March 2026). ENTSO-E, Brussels. Observation year 2025. Accessed 2026-11-03.back
- Global Energy 2026
- Chapter 3
Systems and sectors at baseline
3.1Where each system stood at evidence close
ENE · Energy
Growth in global energy demand
1.3%8 EJ; 2% in 2024.
Reported2025IEA2
ENE · Electricity
Renewables share of generation
33.8%Coal 33.0%.
Reported2025Ember7
CLI · Climate
Energy-related CO2 emissions
>38Gtup about 0.4%; a new record.
Reported2025IEA2
FIN · Finance
Global energy investment
3.4USD trillionestimate; USD 2.6 trillion in 2015.
Reported2026eIEA1
HLT · Health
People without electricity
655millionand about 2.0 billion cook with polluting fuels.
Reported2024SDG 78
SYS · Cross-system
Brent crude, fourth-quarter average (forecast)
91USD a barrelEIA September outlook assumes Middle East flows stay constrained.
Scenario2026EIA47
3.2Domain posture
Each of the twelve coupled domains is read through energy, in words, not scored. The coupling column names the dependency that carries energy risk into each domain.
| Domain | Posture at baseline | Coupling | Status |
|---|---|---|---|
| WAT | Pumping, treatment and desalination need power; hydropower and cooling depend on flows. Volumes of energy-sector water use are not consolidated here. | ENE ↔ WAT | Inferred EQL 2 |
| ENE | Demand up 1.3%, electricity nearly 3%; solar led growth; renewables 33.8% of generation; fuel security under strain. | the core system | Reported EQL 5 |
| FOO | Fertiliser and acid supply chains were hit by the Hormuz closure; cold chains and irrigation depend on power. | ENE → FOO | Reported EQL 3 |
| HLT | 655 million without electricity; about 2.0 billion cook with polluting fuels; heat raises cooling demand. | ENE → HLT | Reported EQL 4 |
| BIO | Mining, hydropower and land for supply chains press on nature; the evidence is not consolidated here. | ENE → BIO | Expert input EQL 2 |
| CLI | Energy CO2 at a record above 38 Gt; weather swings demand for heating and cooling. | ENE → CLI | Reported EQL 5 |
| INF | Grids, pipelines, ports and shipping lanes carry the system; the Iberian blackout shows how voltage control failures cascade. | ENE ↔ INF | Reported EQL 4 |
| FIN | USD 3.4 trillion of annual investment; price spikes and volatility from the 2026 fuel shock. | ENE → FIN | Reported EQL 4 |
| DAT | Grid operators and regulators publish operational data; global coverage is uneven. | DAT → ENE | Expert input EQL 2 |
| AIC | Data centres about 415 TWh in 2024, 945 TWh by 2030 in the base case; clusters concentrate load. | AIC → ENE | Reported EQL 4 |
| MIN | Refining of energy minerals is concentrated; export controls have tripled in scope; copper deficit projected to 2035. | MIN → ENE | Reported EQL 4 |
| TRD | Seaborne oil and LNG trade passes chokepoints; US LNG exports grow; sulphur, aluminium and helium were disrupted. | ENE ↔ TRD | Reported EQL 4 |
3.3Sector screens
All sixteen sectors are screened for their dependence on energy, on the same grammar as every national edition. The evidence column describes coverage of the baseline evidence, not the performance of the sector.
| Code | Sector | Baseline evidence | Exposure to watch | Evidence coverage |
|---|---|---|---|---|
| GS-00 | Cross-system | energy couples every other system83 | fuel shock under heat | PARTIAL |
| GS-01 | Water | pumping, cooling and hydropower depend on each other | drought and heat | THIN |
| GS-02 | Energy | demand 1.3%, electricity nearly 3%2 | fuel shock; grid stress | GOOD |
| GS-03 | Food | fertiliser and sulphur supply disrupted3 | fuel and acid price shock | PARTIAL |
| GS-04 | Health | 655 million without electricity8 | cooling and clinic supply | GOOD |
| GS-05 | Finance | USD 3.4 trillion of investment1 | price volatility | PARTIAL |
| GS-06 | Development | 2.0 billion cook with polluting fuels8 | affordability of access | GOOD |
| GS-07 | Climate | record energy CO2 above 38 Gt2 | weather-driven demand | GOOD |
| GS-08 | Disaster | blackout of 28 April 20259 | cascading outages | PARTIAL |
| GS-09 | Infrastructure | grids, pipelines and ports carry the system1 | equipment lead times | THIN |
| GS-10 | Cities | electrified heat and transport raise load | peak demand | THIN |
| GS-11 | Biodiversity | mining and hydropower pressures | land and flow alteration | THIN |
| GS-12 | Earth observation | weather and satellite data support operations | continuity of missions | THIN |
| GS-13 | Cyber and digital | control systems of utilities35 | attacks on energy systems | THIN |
| GS-14 | Policy | market design and security instruments34 | emergency measures | PARTIAL |
| GS-15 | Science | strong energy-system modelling43 | grid and minerals data | PARTIAL |
Notes
Numbers are the edition’s reference numbers, so a note reads the same in every chapter. The full list, with every source and its licence, is in Annex C. Annex C, references
- 2IEA (ed.), Global Energy Review 2026 (revised version, May 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 7Ember (ed.), Global Electricity Review 2026: 2025 in review (generation, demand, solar, coal). Ember, London. Observation year 2025. Accessed 2026-11-03.back
- 1IEA (ed.), World Energy Investment 2026, launch presentation, Paris, 28 May 2026. International Energy Agency, Paris. Observation year 2026 (estimates, with 2025 data). Accessed 2026-11-03.back
- 8UN DESA Statistics Division (ed.), The Sustainable Development Goals Extended Report 2026, Goal 7 indicator storylines (inputs as of 30 April 2026). United Nations, New York. Observation year 2024. Accessed 2026-11-03.back
- 47US Energy Information Administration (ed.), Short-Term Energy Outlook, September 2026 (Brent about USD 91 a barrel in the fourth quarter of 2026; Middle East oil flows assumed constrained through the fourth quarter of 2026). EIA, Washington. Observation year 2026. Accessed 2026-11-03.back
- 3IEA (ed.), Global Critical Minerals Outlook 2026 (revised version, July 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 9ENTSO-E (ed.), 28 April 2025 Iberian blackout: final report of the expert panel (publication page; report dated 20 March 2026). ENTSO-E, Brussels. Observation year 2025. Accessed 2026-11-03.back
- 35UNVERIFIED, not opened: Commission Delegated Regulation (EU) 2024/1366 establishing a network code on cybersecurity aspects of cross-border electricity flows, Official Journal of the European Union, 2024, cited from memory. Observation year 2024. Accessed 2026-11-03.back
- 34UNVERIFIED, not opened: Regulation (EU) 2024/1747 amending Regulations (EU) 2019/942 and (EU) 2019/943 on the electricity market design, Official Journal of the European Union, 2024, cited from memory. Observation year 2024. Accessed 2026-11-03.back
- 43UNVERIFIED, not opened: Davis, S.J. et al., Net-zero emissions energy systems, Science 360(6396), eaas9793, 2018, cited from memory. American Association for the Advancement of Science. Observation year 2018. Accessed 2026-11-03.back
- Global Energy 2026
- Chapter 4
Risks and capability
Four energy risk objects open the portfolio. Order carries no rank. Each is read across driver, exposure, vulnerability, capacity, cascade and consequence.
4.1Risk objects
Each risk is read across the chain from hazard to consequence, with its status and evidence-quality level.
ReportedEQL 4RSK-GS02-ENE-001
Seaborne oil and LNG chokepoint disruption
- Driver
- conflict-related closure or damage affecting Hormuz flows and Qatari LNG1113
- Exposure
- importing economies, refiners, power systems burning gas or oil
- Vulnerability
- thin spare capacity; limited bypass routes
- Capacity
- emergency stocks; bypass pipelines; demand response12
- Cascade
- ENE → FIN, FOO, HLT
- Horizon
- 1 to 3 years
InferredEQL 3RSK-GS02-INF-002
Power-system stability with high inverter-based supply
- Driver
- rapid change in the generation mix and voltage control gaps9
- Exposure
- synchronous grids and large cities
- Vulnerability
- uneven stabilisation capability; coordination gaps
- Capacity
- reactive power requirements; grid-forming equipment; operator coordination
- Cascade
- ENE → HLT, WAT, INF
- Horizon
- 1 to 5 years
ReportedEQL 4RSK-GS02-MIN-003
Critical-mineral export controls and refining concentration
InferredEQL 3RSK-GS02-AIC-004
Concentrated data-centre load on local grids
4.2Capability ladder
Existence is not readiness. Each of the fifteen capability functions is placed on the ladder by the strongest public evidence for energy at the global level.
| Function | Rung | Level | Strongest public evidence at baseline |
|---|---|---|---|
| Prevention and mitigation | EXISTS | efficiency and reliability standards widespread; implementation uneven2436 | |
| Monitoring and observation | ADEQUATE | market and operational data strong in advanced grids; thin elsewhere79 | |
| Early warning | EXISTS | weather-linked demand forecasts and grid alerts; fuel-market early warning is partial | |
| Preparedness and planning | EXISTS | adequacy assessments published for several grids30 | |
| Redundancy and reserves | DEMONSTRATED | record coordinated oil stock release in March 202612 | |
| Response | DEMONSTRATED | emergency measures and demand response used in 2022 and 202612 | |
| Continuity of critical services | EXISTS | priority supply for hospitals and water works in many systems; testing uneven | |
| Recovery | DEMONSTRATED | Iberian system restored after the 2025 blackout; reasons studied in a final report9 | |
| Adaptation | EXISTS | storage, flexibility and diversified supply growing27 | |
| Social protection | LISTED | energy support for poor households documented but not consolidated | |
| Finance and insurance | EXISTS | investment of USD 3.4 trillion; public finance for minerals rising13 | |
| Institutional coordination | EXISTS | IEA collective action; network codes in the EU1235 | |
| Technical infrastructure | EXISTS | grids ageing in places; equipment lead times a constraint22 | |
| Workforce | LISTED | skills gaps reported across the energy sector23 | |
| Research capacity | ADEQUATE | strong energy-system science; data access uneven43 | |
| A capability listed in policy is not a tested one; each rung is the strongest public evidence at baseline. | |||
Notes
Numbers are the edition’s reference numbers, so a note reads the same in every chapter. The full list, with every source and its licence, is in Annex C. Annex C, references
- 11UNVERIFIED, not opened: IEA (ed.), Oil Market Report, September 2026; flows through the strait of 7.6 mb/d in August, 2026 supply 100.7 mb/d and demand 102.5 mb/d, and taken from search-result summaries. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 13UNVERIFIED, not opened: IEA (ed.), Gas Market Report, Q2-2026; Ras Laffan offline since early March 2026 and nearly a fifth of global LNG supply removed, taken from search-result summaries. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 12UNVERIFIED, not opened: IEA (ed.), collective action on emergency oil stocks agreed on 11 March 2026 (400 million barrels, the largest release in the agency’s history), with export volumes through the strait below 10% of pre-conflict levels and pre-war flows of about 20 mb/d, taken from search-result summaries; the release itself is also noted in the opened minerals outlook [3]. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 9ENTSO-E (ed.), 28 April 2025 Iberian blackout: final report of the expert panel (publication page; report dated 20 March 2026). ENTSO-E, Brussels. Observation year 2025. Accessed 2026-11-03.back
- 3IEA (ed.), Global Critical Minerals Outlook 2026 (revised version, July 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 4IEA (ed.), Energy and AI (World Energy Outlook Special Report). International Energy Agency, Paris, April 2025. Observation year 2024. Accessed 2026-11-03.back
- 24UNVERIFIED, not opened: IEA (ed.), Energy Efficiency 2025. International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 36UNVERIFIED, not opened: ISO 50001:2018, Energy management systems: requirements with guidance for use. International Organization for Standardization, Geneva. Observation year 2018. Accessed 2026-11-03.back
- 7Ember (ed.), Global Electricity Review 2026: 2025 in review (generation, demand, solar, coal). Ember, London. Observation year 2025. Accessed 2026-11-03.back
- 30UNVERIFIED, not opened: NERC (ed.), Long-Term Reliability Assessment, 2025 edition, North American Electric Reliability Corporation, Atlanta, cited from memory. Observation year 2025. Accessed 2026-11-03.back
- 2IEA (ed.), Global Energy Review 2026 (revised version, May 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 1IEA (ed.), World Energy Investment 2026, launch presentation, Paris, 28 May 2026. International Energy Agency, Paris. Observation year 2026 (estimates, with 2025 data). Accessed 2026-11-03.back
- 35UNVERIFIED, not opened: Commission Delegated Regulation (EU) 2024/1366 establishing a network code on cybersecurity aspects of cross-border electricity flows, Official Journal of the European Union, 2024, cited from memory. Observation year 2024. Accessed 2026-11-03.back
- 22UNVERIFIED, not opened: IEA (ed.), Electricity Grids and Secure Energy Transitions. International Energy Agency, Paris, 2023. Observation year 2023. Accessed 2026-11-03.back
- 23UNVERIFIED, not opened: IEA (ed.), World Energy Employment 2025. International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 43UNVERIFIED, not opened: Davis, S.J. et al., Net-zero emissions energy systems, Science 360(6396), eaas9793, 2018, cited from memory. American Association for the Advancement of Science. Observation year 2018. Accessed 2026-11-03.back
- Global Energy 2026
- Chapter 5
Fuel supply shock under a hot, high-demand season
A conditional statement under stated assumptions, never a prediction.
5.1Assumptions
Scenario SCN-GS02-LNG-01: what is assumed, and what is held constant.
- Baseline
- the 2026 reference state in this edition
- Drivers
- a disruption to seaborne oil and LNG supply that coincides with a heat wave and high cooling demand in several importing regions
- Analogues
- 2022 energy crisis; the 2026 Hormuz disruption4711
- Interventions
- none modelled: the specification describes the unmitigated case
- Run state
- narrative specification; quantified run scheduled for 2027
5.2The cascade, step by step
- 1
TRD → ENE
seaborne oil and LNG supply falls; spot prices rise
2022 · 2026
- 2
CLI → ENE
heat raises cooling demand while hydro and thermal output are limited
2022
- 3
ENE → INF
voltage and frequency control tighten; outage risk rises
2025
- 4
ENE → FOO
fuel and fertiliser costs reach farms and food prices
2022 · 2026
- 5
ENE → HLT
rationing and outages affect clinics, cooling and cold chains
2025
- 6
ENE → FIN
import bills and subsidies strain public budgets
2022
5.3The scenario as a table of steps
How the shock in scenario SCN-GS02-LNG-01 would travel through Global Energy’s coupled systems, step by step, under the assumptions the edition states.
| Step | What happens | Source |
|---|---|---|
| 01 Trade to energy | Seaborne oil and LNG supply falls; spot prices rise. Analogue or source: 2022 · 2026. | Edition GS-02, scenario SCN-GS02-LNG-01, step 1 |
| 02 Climate to energy | Heat raises cooling demand while hydro and thermal output are limited. Analogue or source: 2022. | Edition GS-02, scenario SCN-GS02-LNG-01, step 2 |
| 03 Energy to infrastructure | Voltage and frequency control tighten; outage risk rises. Analogue or source: 2025. | Edition GS-02, scenario SCN-GS02-LNG-01, step 3 |
| 04 Energy to food | Fuel and fertiliser costs reach farms and food prices. Analogue or source: 2022 · 2026. | Edition GS-02, scenario SCN-GS02-LNG-01, step 4 |
| 05 Energy to health | Rationing and outages affect clinics, cooling and cold chains. Analogue or source: 2025. | Edition GS-02, scenario SCN-GS02-LNG-01, step 5 |
| 06 Energy to finance | Import bills and subsidies strain public budgets. Analogue or source: 2022. | Edition GS-02, scenario SCN-GS02-LNG-01, step 6 |
A teaching model of a conditional scenario under the edition’s stated assumptions: not a forecast, not a prediction and not a warning. Sources: Global Energy 2026, scenario SCN-GS02-LNG-01 (2026); Global Energy 2026, references (NR-CIT-1) (2026).
Notes
Numbers are the edition’s reference numbers, so a note reads the same in every chapter. The full list, with every source and its licence, is in Annex C. Annex C, references
- 47US Energy Information Administration (ed.), Short-Term Energy Outlook, September 2026 (Brent about USD 91 a barrel in the fourth quarter of 2026; Middle East oil flows assumed constrained through the fourth quarter of 2026). EIA, Washington. Observation year 2026. Accessed 2026-11-03.back
- 11UNVERIFIED, not opened: IEA (ed.), Oil Market Report, September 2026; flows through the strait of 7.6 mb/d in August, 2026 supply 100.7 mb/d and demand 102.5 mb/d, and taken from search-result summaries. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- Global Energy 2026
- Chapter 6
Readings from the other desks
The energy baseline is read through each steward’s lens, then once as a whole. Each lens is a projection of reviewed findings, not a separate argument. The other desks’ own editions of this subject are listed first, as cross-references, not copies.
6.1The other desks’ editions of this subject
Federation: each desk writes its own edition for the subjects in its remit. Until a desk releases, its edition shows its frame and the reading this edition printed for it.
| Desk | Edition | State | Identifier |
|---|---|---|---|
| GCRI Systems Evidence | No edition of this subject at this desk in the 2026 Baseline cycle | Not in this cycle | |
| GRF Public Deliberation | Outside this desk’s remit | Not in remit | |
| GRA Capital Readiness | No edition of this subject at this desk in the 2026 Baseline cycle | Not in this cycle | |
| Standards Progress | No edition of this subject at this desk in the 2026 Baseline cycle | Not in this cycle | |
| Academy Capability | No edition of this subject at this desk in the 2026 Baseline cycle | Not in this cycle | |
| Index Measurement | Outside this desk’s remit | Not in remit |
6.2Three lenses
One edition, read by each steward. The lens of this site comes first.
GCRI · KEY T
Technical Truth
The evidence supports reading energy as the coupling layer of the WEFH+B system. Demand and electrification are rising, supply is changing fastest at the margin, and security of supply is the sharpest pressure. Evidence is strongest for demand and generation, and weakest for grid constraints and energy-sector water use.
ENE-001 · ENE-003 · GOV-008 · SYS-012
GRF · KEY M
Public Meaning
For most people energy risk arrives as a power cut, a higher bill or a cooking fire. The baseline asks that public debate treat energy as shared infrastructure for health, food and water, and keep the 655 million without electricity in view alongside the security story.
HLT-007 · GOV-008 · ENE-001
GRA · KEY F
Capital Meaning
Readiness implications only. Investment is high, price volatility has risen and public finance for minerals is growing13. These show where finance-readiness evidence will matter. Nothing here is advice, a rating or an approval.
FIN-005 · MIN-010
NEXUS
Synthesis
The energy system is well measured at the level of demand and generation and thinly measured at the level of equipment, constraints and water. The 2027 programme should bind regional grid evidence, test the fuel shock under heat, and map mineral chokepoints before they become delays.
SYS-012 · E-01 · E-04
6.3Standards, Academy and steward contributions
How the Nexus Standards drafts, the Risk Academy and the three stewards feed each quarterly edition for energy. The standards are a preparatory working draft (2026) and are cited as drafts, never as adopted standards.
| Quarter | Edition | Question | Boundary |
|---|---|---|---|
| Q1 | State and Agenda | What matters this year, and what is the starting position? | observed baseline stays distinct from planned work |
| Q2 | Evidence and Build | What new evidence and capability exist? | a configured capability is not a validated result |
| Q3 | Stress Test and Readiness | What do scenarios and tests show? | simulated loss or performance is not observed impact |
| Q4 | Annual Synthesis and Renewal | What changed in the year, and what renews? | release follows review, not event publicity deadlines |
| Steward or body | Role | Contribution route |
|---|---|---|
| GCRI Canada | Lead Institution and Consortium Secretariat; publisher of record; technical truth (key T) | science and practice communities · GCRI gateway |
| The Global Risks Forum (GRF) | leadership, dialogue and the Universe programme; public meaning (key M) | policy, Universe and national adoption · GRF gateway |
| The Global Risks Alliance (GRA) | finance, insurance and development readiness; capital meaning (key F) | finance and insurance · GRA gateway |
| Nexus Standards | preparatory drafts on vocabulary, hazards, indicators and methods | Standards site · working groups HAZ, IND, MTH, FIN, AI |
| Risk Academy | learning pathways tied to the agenda questions | Academy gateway · learning by review |
| Reports sector desks | energy chapter inputs: GCRI evidence, GRA readiness, NXS standards, RA capability | sector editorial board |
Standards drafts used in this edition
- Risk vocabulary NRS-C1 (424 terms) for terms in the glossary
- Hazard atlas NHS-1 1.1.0 (905 hazards in 120 families) for risk objects
- Seven risk classes: global, catastrophic, existential, emerging, planetary, exponential, frontier-tech
Standards calendar to watch
- Founding calls from 20 October 2026; working groups meet from 5 November 2026
- Inaugural Global Standards Council session, 12 January 2027
- Quarterly reviews in March, June, September and December, aligned with each edition
6.4GCRI reading: the model card
GCRI’s reading of this edition is its model card: what the national model is, what it computes and where it stops. It is printed in full in Annex A, with the methods it belongs to. Annex A, methodology
6.5Global Risks Forum reading: editorial essays
Four signed essays by the Reports editorial team set out the positions this edition takes. They are interpretation, labelled as such; the evidence they draw on is in the findings register.
Every energy shock this decade has been a water event, a food event and a health event at once. Treating energy as a utility market understates how it carries risk between systems. This edition asks where an energy shock goes next.
EDITORIAL ESSAY · 01
Energy is a coupling, not a sector
The 2026 disruption began in oil and LNG and reached aluminium, sulphur and helium within weeks. Security of supply now spans fuels, minerals and equipment. Measuring the whole chain is the first adaptation.
EDITORIAL ESSAY · 02
Security is wider than oil
Electricity grew more than twice as fast as energy demand. Risk moves with it: from fuel tankers to voltage control, equipment queues and data-centre clusters. The Iberian blackout is an early lesson, not a verdict on any technology.
EDITORIAL ESSAY · 03
Electrification moves the risk to the grid
The 655 million without electricity and the 2.0 billion cooking with polluting fuels sit outside most security debates. Closing the gaps is not separate from resilience; it is part of it.
EDITORIAL ESSAY · 04
Access is the unfinished half
6.6Global Risks Alliance reading: 2027 energy readiness pack
The registers that open the 2027 global cycle. At baseline each is initialised from this edition.
| Item | Register | State at baseline | First 2027 entry |
|---|---|---|---|
| E1 | Energy risk state delta | baseline set by this edition | changes against the baseline |
| E2 | WEFH+B state delta | five global system readings set | indicator updates and freshness |
| E3 | Agenda and Portfolio movement | eight agenda items · 6 proposed objects | admission decisions |
| E4 | Federation delivery register | national chapters in preparation | national chapters |
| E5 | Consortium capability register | national consortia forming | first contributions |
| E6 | Leadership questions and challenges | none yet | first challenge log |
| E7 | Foundry technical state | national environments prepared | first federation cut |
| E8 | Publication candidates | twelve findings carried forward | PUBLISH · HOLD dispositions |
| E9 | Universe readiness | one candidate mission | admission and role spine |
| E10 | Correction register | none | first federation-wide cycle |
Publication dispositions
- Publish
- Hold
- Needs evidence
- Restricted
- Superseded
6.7Nexus Standards reading: standards and regulatory watch
Instruments and published guidance that shape the systems in this edition, by status on the retrieval date. The edition assesses no one’s compliance.
- IN FORCE
- ADOPTED
- PUBLISHED · GUIDANCE
- PUBLISHED · VOLUNTARY
| Instrument | Body | Scope | Status | Relevance |
|---|---|---|---|---|
| Global Stocktake decision (tripling renewables, transition away from fossil fuels)20 | UNFCCC | global | ADOPTED 2023 | targets |
| Critical Raw Materials Act33 | European Union | EU | IN FORCE | minerals |
| Electricity market design regulation34 | European Union | EU | IN FORCE | markets |
| Network code on electricity cybersecurity35 | European Union | EU | IN FORCE | cyber |
| ISO 50001 energy management36 | ISO | global | PUBLISHED · VOLUNTARY | efficiency |
| IEC 62443 control-system security37 | IEC | global | PUBLISHED · VOLUNTARY | cyber |
| IEA collective action on emergency oil stocks12 | IEA members | 32 members | USED MARCH 2026 | oil security |
Changed since 2024
6.8Risk Academy reading: literature and evidence review, science and assessments
The review behind this edition covers energy assessments, peer-reviewed science and the institutional reports that bind its findings. Systematic reviews for each agenda item begin in 2027.
Review protocol
- Question
- What does the published evidence establish about the world’s energy system and its couplings?
- Sources searched
- agency flagships; regulator and operator reports; peer-reviewed energy-system literature; statistics
- Window
- releases available at evidence close, 30 September 2026
- Selection
- sources that bind or contextualise a finding in this edition
- Next step
- systematic reviews for agenda items 01 to 05 in 2027
| Reference | Type | Year | Role | Used for |
|---|---|---|---|---|
| Davis et al.43 | journal article | 2018 | framework | hard-to-decarbonise sectors |
| Creutzig et al.44 | journal article | 2018 | context | demand-side options |
| Ueckerdt et al.45 | journal article | 2021 | context | electro-fuels |
| Zscheischler et al.46 | journal article | 2018 | framework | compound events |
| IPCC AR6 Working Group III19 | assessment | 2022 | context | mitigation pathways |
| Net Zero Roadmap, 2023 update21 | assessment | 2023 | context | pathway benchmark |
| UNEP Emissions Gap Report31 | assessment | 2025 | context | emissions trajectory |
| Production Gap Report32 | assessment | 2023 | context | fossil supply plans |
| Reference | Issuer | Year | Role | Used for |
|---|---|---|---|---|
| Global Energy Review 20262 | IEA | 2026 | supports | demand, emissions |
| World Energy Investment 20261 | IEA | 2026 | supports | investment |
| Global Critical Minerals Outlook 20263 | IEA | 2026 | supports | minerals |
| Energy and AI4 | IEA | 2025 | supports | data centres |
| World Energy Outlook 20256 | IEA | 2025 | context | scenarios |
| Renewables 202539 | IEA | 2025 | context | capacity outlook |
| Global Hydrogen Review 202540 | IEA | 2025 | context | low-emissions fuels |
| Global Methane Tracker 202541 | IEA | 2025 | context | methane from energy |
| Energy Technology Perspectives 202442 | IEA | 2024 | context | clean-tech supply chains |
| Reference | Issuer | Year | Role | Used for |
|---|---|---|---|---|
| SDG Extended Report, Goal 78 | UN DESA | 2026 | supports | access |
| Global Electricity Review 20267 | Ember | 2026 | supports | generation |
| Statistical Review 202615 | Energy Institute | 2026 | context | primary energy |
| Renewable capacity statistics14 | IRENA | 2026 | context | capacity |
| Short-Term Energy Outlook47 | EIA | 2026 | supports | prices and flows |
| Electricity Mid-Year Update 202616 | IEA | 2026 | context | demand outlook |
| World Energy Transitions Outlook 202427 | IRENA | 2024 | context | transition pathway |
| Reference | Issuer | Year | Role | Used for |
|---|---|---|---|---|
| Iberian blackout final report9 | ENTSO-E | 2026 | supports | grid failure |
| Electricity Grids and Secure Energy Transitions22 | IEA | 2023 | context | grid needs |
| Long-Term Reliability Assessment30 | NERC | 2025 | context | adequacy |
| Gas Market Report513 | IEA | 2025 to 2026 | supports | LNG |
| Oil Market Report11 | IEA | 2026 | supports | oil flows |
| Critical Raw Materials Act33 | European Union | 2024 | context | minerals policy |
| US data centre energy report18 | Berkeley Lab | 2024 | context | load growth |
| Oil 202525 and Electricity 202526 | IEA | 2025 | context | outlooks |
| Nuclear power estimates to 205029 | IAEA | 2025 | context | nuclear |
| Climate Resilience for Energy Security38 | IEA | 2022 | context | resilience |
Where the evidence agrees
Notes
Numbers are the edition’s reference numbers, so a note reads the same in every chapter. The full list, with every source and its licence, is in Annex C. Annex C, references
- 1IEA (ed.), World Energy Investment 2026, launch presentation, Paris, 28 May 2026. International Energy Agency, Paris. Observation year 2026 (estimates, with 2025 data). Accessed 2026-11-03.back
- 3IEA (ed.), Global Critical Minerals Outlook 2026 (revised version, July 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 20UNVERIFIED, not opened: UNFCCC (ed.), Outcome of the first global stocktake, decision 1/CMA.5 (December 2023; tripling renewable capacity and transitioning away from fossil fuels in energy systems), cited from memory. UNFCCC, Bonn. Observation year 2023. Accessed 2026-11-03.back
- 33UNVERIFIED, not opened: Regulation (EU) 2024/1252 establishing a framework for a secure and sustainable supply of critical raw materials (Critical Raw Materials Act), Official Journal of the European Union, 2024, cited from memory. Observation year 2024. Accessed 2026-11-03.back
- 34UNVERIFIED, not opened: Regulation (EU) 2024/1747 amending Regulations (EU) 2019/942 and (EU) 2019/943 on the electricity market design, Official Journal of the European Union, 2024, cited from memory. Observation year 2024. Accessed 2026-11-03.back
- 35UNVERIFIED, not opened: Commission Delegated Regulation (EU) 2024/1366 establishing a network code on cybersecurity aspects of cross-border electricity flows, Official Journal of the European Union, 2024, cited from memory. Observation year 2024. Accessed 2026-11-03.back
- 36UNVERIFIED, not opened: ISO 50001:2018, Energy management systems: requirements with guidance for use. International Organization for Standardization, Geneva. Observation year 2018. Accessed 2026-11-03.back
- 37UNVERIFIED, not opened: IEC 62443 series, Security for industrial automation and control systems. International Electrotechnical Commission, Geneva. Observation year 2018. Accessed 2026-11-03.back
- 12UNVERIFIED, not opened: IEA (ed.), collective action on emergency oil stocks agreed on 11 March 2026 (400 million barrels, the largest release in the agency’s history), with export volumes through the strait below 10% of pre-conflict levels and pre-war flows of about 20 mb/d, taken from search-result summaries; the release itself is also noted in the opened minerals outlook [3]. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 9ENTSO-E (ed.), 28 April 2025 Iberian blackout: final report of the expert panel (publication page; report dated 20 March 2026). ENTSO-E, Brussels. Observation year 2025. Accessed 2026-11-03.back
- 28UNVERIFIED, not opened: IRENA (ed.), Tracking COP28 outcomes: tripling renewable power capacity and doubling energy efficiency by 2030. International Renewable Energy Agency, Abu Dhabi, 2024. Observation year 2024. Accessed 2026-11-03.back
- 43UNVERIFIED, not opened: Davis, S.J. et al., Net-zero emissions energy systems, Science 360(6396), eaas9793, 2018, cited from memory. American Association for the Advancement of Science. Observation year 2018. Accessed 2026-11-03.back
- 44UNVERIFIED, not opened: Creutzig, F. et al., Towards demand-side solutions for mitigating climate change, Nature Climate Change 8, 260 to 263, 2018, cited from memory. Springer Nature. Observation year 2018. Accessed 2026-11-03.back
- 45UNVERIFIED, not opened: Ueckerdt, F. et al., Potential and risks of hydrogen-based e-fuels in climate change mitigation, Nature Climate Change 11, 384 to 393, 2021, cited from memory. Springer Nature. Observation year 2021. Accessed 2026-11-03.back
- 46UNVERIFIED, not opened: Zscheischler, J. et al., Future climate risk from compound events, Nature Climate Change 8, 469 to 477, 2018, cited from memory. Springer Nature. Observation year 2018. Accessed 2026-11-03.back
- 19UNVERIFIED, not opened: Shukla, P.R. et al. (eds.), Climate Change 2022: Mitigation of Climate Change, Contribution of Working Group III to the Sixth Assessment Report. IPCC, Geneva, 2022. Observation year 2022. Accessed 2026-11-03.back
- 21UNVERIFIED, not opened: IEA (ed.), Net Zero Roadmap: A Global Pathway to Keep the 1.5 °C Goal in Reach, 2023 update. International Energy Agency, Paris. Observation year 2023. Accessed 2026-11-03.back
- 31UNVERIFIED, not opened: UNEP (ed.), Emissions Gap Report 2025. United Nations Environment Programme, Nairobi. Observation year 2025. Accessed 2026-11-03.back
- 32UNVERIFIED, not opened: SEI, Climate Analytics, E3G, IISD and UNEP (eds.), The Production Gap Report 2023. Stockholm Environment Institute, Stockholm. Observation year 2023. Accessed 2026-11-03.back
- 2IEA (ed.), Global Energy Review 2026 (revised version, May 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 4IEA (ed.), Energy and AI (World Energy Outlook Special Report). International Energy Agency, Paris, April 2025. Observation year 2024. Accessed 2026-11-03.back
- 6IEA (ed.), World Energy Outlook 2025, launch presentation, Paris, 12 November 2025. International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 39UNVERIFIED, not opened: IEA (ed.), Renewables 2025: Analysis and forecasts to 2030. International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 40UNVERIFIED, not opened: IEA (ed.), Global Hydrogen Review 2025. International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 41UNVERIFIED, not opened: IEA (ed.), Global Methane Tracker 2025. International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 42UNVERIFIED, not opened: IEA (ed.), Energy Technology Perspectives 2024. International Energy Agency, Paris. Observation year 2024. Accessed 2026-11-03.back
- 8UN DESA Statistics Division (ed.), The Sustainable Development Goals Extended Report 2026, Goal 7 indicator storylines (inputs as of 30 April 2026). United Nations, New York. Observation year 2024. Accessed 2026-11-03.back
- 7Ember (ed.), Global Electricity Review 2026: 2025 in review (generation, demand, solar, coal). Ember, London. Observation year 2025. Accessed 2026-11-03.back
- 15UNVERIFIED, not opened: Energy Institute (ed.), Statistical Review of World Energy 2026 (75th edition; fossil fuels about 86% of primary energy, hydropower 2.7%, electricity demand up 3%); values taken from a trade-press summary that was opened, not from the Review. Energy Institute, London. Observation year 2025. Accessed 2026-11-03.back
- 14UNVERIFIED, not opened: IRENA (ed.), Renewable Capacity Statistics 2026 (about 692 GW added in 2025; 5,149 GW total), taken from search-result summaries; the page returned an access error. International Renewable Energy Agency, Abu Dhabi. Observation year 2025. Accessed 2026-11-03.back
- 47US Energy Information Administration (ed.), Short-Term Energy Outlook, September 2026 (Brent about USD 91 a barrel in the fourth quarter of 2026; Middle East oil flows assumed constrained through the fourth quarter of 2026). EIA, Washington. Observation year 2026. Accessed 2026-11-03.back
- 16UNVERIFIED, not opened: IEA (ed.), Electricity Mid-Year Update 2026 (23 July 2026; demand growth 3.6% in 2026 and 3.8% in 2027 in search summaries); no figure from it is used in a finding. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 27UNVERIFIED, not opened: IRENA (ed.), World Energy Transitions Outlook 2024. International Renewable Energy Agency, Abu Dhabi. Observation year 2024. Accessed 2026-11-03.back
- 22UNVERIFIED, not opened: IEA (ed.), Electricity Grids and Secure Energy Transitions. International Energy Agency, Paris, 2023. Observation year 2023. Accessed 2026-11-03.back
- 30UNVERIFIED, not opened: NERC (ed.), Long-Term Reliability Assessment, 2025 edition, North American Electric Reliability Corporation, Atlanta, cited from memory. Observation year 2025. Accessed 2026-11-03.back
- 5IEA (ed.), Gas 2025: Analysis and forecasts to 2030 (Gas Market Report, Q4-2025). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 13UNVERIFIED, not opened: IEA (ed.), Gas Market Report, Q2-2026; Ras Laffan offline since early March 2026 and nearly a fifth of global LNG supply removed, taken from search-result summaries. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 11UNVERIFIED, not opened: IEA (ed.), Oil Market Report, September 2026; flows through the strait of 7.6 mb/d in August, 2026 supply 100.7 mb/d and demand 102.5 mb/d, and taken from search-result summaries. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 18UNVERIFIED, not opened: Shehabi, A. et al., 2024 United States Data Center Energy Usage Report, Lawrence Berkeley National Laboratory, Berkeley, December 2024; the page returned an access error and no figure is used. Observation year 2023. Accessed 2026-11-03.back
- 25UNVERIFIED, not opened: IEA (ed.), Oil 2025: Analysis and forecast to 2030. International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 26UNVERIFIED, not opened: IEA (ed.), Electricity 2025: Analysis and forecast to 2027. International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 29UNVERIFIED, not opened: IAEA (ed.), Energy, Electricity and Nuclear Power Estimates for the Period up to 2050, 2025 edition. International Atomic Energy Agency, Vienna. Observation year 2025. Accessed 2026-11-03.back
- 38UNVERIFIED, not opened: IEA (ed.), Climate Resilience for Energy Security. International Energy Agency, Paris, 2022. Observation year 2022. Accessed 2026-11-03.back
- Global Energy 2026
- Chapter 7
The 2027 agenda
Eight bounded questions open the 2027 energy agenda. Each comes from a baseline finding, names the initiative that will carry it and the first output due in the 2027 energy edition.
7.1Questions for the operational series
- E-01
How would a fuel supply shock that coincides with a hot season and grid stress travel through power, food and health at once?
INI-GS02-FSH-01 · fuel shock under heat; first output: concurrency analysis for six regions.
- E-02
Where do grid equipment and interconnection constraints limit the connection of new supply and load?
INI-GS02-GRD-02 · grid constraints; first output: constraint register by region.
- E-03
How much water do energy supply and data centres need by 2030, and where?
INI-GS02-WEN-03 · water for energy and compute; first output: regional demand estimates.
- E-04
Which critical minerals and refining steps are single points of failure for power equipment?
INI-GS02-MIN-04 · mineral chokepoints; first output: dependence map.
- E-05
Where do energy access gaps coincide with weak service quality, and what is the cost of closing them?
INI-GS02-ACC-05 · access and service quality; first output: service-tier table.
- E-06
Which shared grids and fuel routes lack operational contingency arrangements?
To be admitted in 2027; first output: arrangement overlay.
- E-07
How do heat waves change peak demand and supply together?
To be admitted in 2027; first output: scoping note.
- E-08
Which energy capabilities have been tested in real shortfalls, and which are only planned?
Energy capability register; first output: rung evidence for 15 functions.
7.2Portfolio proposed for the Q1 2027 alignment
Five initiatives and one Universe mission candidate are proposed for the 2027 energy portfolio. They are programme objects: no partner, funder or member is attached to them in this edition.
| ID | Object | Kind | Question | State |
|---|---|---|---|---|
| INI-GS02-FSH-01 | Fuel shock under heat | Initiative | E-01 | PROPOSED |
| INI-GS02-GRD-02 | Grid and interconnection constraints | Initiative | E-02 | PROPOSED |
| INI-GS02-WEN-03 | Water for energy and compute | Initiative | E-03 | PROPOSED |
| INI-GS02-MIN-04 | Mineral chokepoints | Initiative | E-04 | PROPOSED |
| INI-GS02-ACC-05 | Access and service quality | Initiative | E-05 | PROPOSED |
| MSN-GS02-2027-01 | Fuel shock under heat Universe mission | Mission | E-01 | Candidate |
7.3The pathway
The energy edition reads national energy chapters, regional grid and fuel evidence and the global edition through one governed evidence graph. At baseline the federation is designed; the Canada and global energy chapters are drafted. This page states what exists today and what comes next.
- 01
National energy chapters
energy system of each national edition
DRAFTED · further national baselines
- 02
Grid and fuel evidence
shared grids, pipelines and sea routes
PLANNED · regional Baseline Editions
- 03
Energy sector model
the global energy system of systems
v0 SPECIFIED · v1 with federation evidence
- 04
Global and strategic links
GLB · SR-02 Critical Infrastructure and Lifeline Systems · SR-04 Critical Minerals and Strategic Materials
PLANNED · strategic baselines
- 05
Universe
annual proving environment
CANDIDATE MISSION · mandate in 2027
- 06
Global Energy Report
this series
BASELINE DRAFT · 2027 annual edition
- 07
Evidence and correction
one graph, many projections
OPEN · first correction cycle in 2027
7.4Universe 2027: evidence pack for the energy candidate mission
- 01
Mandate
- 02
Core Build · 1 month
- 03
Action · 1 week
- 04
Evidence seal
- 05
Portfolio correction
- 06
Next mandate
| Item | Record | State | Timing |
|---|---|---|---|
| F1 | Annual mandate record | PLANNED | after the Q2 2027 alignment |
| F2 | Core Build record | PLANNED | one month before the exercise |
| F3 | Exercise evidence | PLANNED | during the Action week |
| F4 | Decision packets | PLANNED | exercise state only |
| F5 | Proof receipts | PLANNED | scoped to each recorded check |
| F6 | After-action report | PLANNED | within one quarter |
| F7 | Upgrade docket | PLANNED | routed to the Portfolio |
| F8 | Portfolio renewal | PLANNED | 2027 global annual edition |
| F9 | Public synthesis | PLANNED | public-safe extracts only |
Mission
- ID
- MSN-GS02-2027-01 · Fuel shock under heat Universe mission
- Role spine
- Leadership sponsor · Institutional anchor · Mission lead: drawn from national pathways
- Receiving actors
- to be identified with the mandate
7.5Handoffs and routing
Where the baseline’s findings go next. A handoff routes a finding for awareness, review or work; it transfers no authority.
| Finding | Routed to | Purpose | Class |
|---|---|---|---|
| ENE-001 · demand | public record | reference for the 2027 series | PUBLIC |
| ENE-003 · electricity | INI-GS02-GRD-02 | grid constraints | PUBLIC |
| AIC-006 · data centres | INI-GS02-WEN-03 | water for energy and compute | PUBLIC |
| HLT-007 · access | INI-GS02-ACC-05 | access and service quality | PUBLIC |
| GOV-008 · fuel flows | INI-GS02-FSH-01 · key F review | fuel shock under heat | PUBLIC |
| MIN-010 · minerals | INI-GS02-MIN-04 | mineral chokepoints | PUBLIC |
| INF-011 · grid failure | regional consortia | grid constraint overlay | PUBLIC |
| SYS-012 · compound pathway | MSN-GS02-2027-01 | Universe candidate | CONSORTIUM |
| Class | Where it goes | Who can see it |
|---|---|---|
| PUBLIC | the published edition and its evidence bundle | anyone |
| CONSORTIUM | governed rooms of the federation | consortium members under agreement |
| CONTROLLED | need-to-know channels | named competent actors only |
7.6Feeds and signal register
| Feed | Producer | Latency | Feeds into |
|---|---|---|---|
| Electricity data and the Global Electricity Review | Ember | annual | ENE-003 |
| Oil and gas market reports | IEA | monthly and quarterly | GOV-008 |
| Short-Term Energy Outlook | US Energy Information Administration | monthly | GOV-008 |
| Transparency platform for the continental grid | ENTSO-E | hourly | INF-011 |
| Critical minerals outlook | IEA | annual | MIN-010 |
| SDG 7 tracking database | World Bank, IEA, IRENA, UNSD, WHO | annual | HLT-007 |
| Renewable capacity statistics | IRENA | annual | ENE-002 |
Escalation routes
- none · keep monitoring
- research question
- project
- risk object
- annual publication
- signal report
| ID | Signal | Corroboration | Systems | Route |
|---|---|---|---|---|
| SIG-GS02-001 | Oil flows through Hormuz fell from March 20264711 | CORROBORATED | ENE · FIN | research question E-01 |
| SIG-GS02-002 | Mineral export controls tripled in scope since 20233 | CORROBORATED | MIN · ENE | initiative E-04 |
| SIG-GS02-003 | Data-centre load growth in clusters4 | PARTIAL | AIC · ENE | research question E-03 |
Notes
Numbers are the edition’s reference numbers, so a note reads the same in every chapter. The full list, with every source and its licence, is in Annex C. Annex C, references
- 47US Energy Information Administration (ed.), Short-Term Energy Outlook, September 2026 (Brent about USD 91 a barrel in the fourth quarter of 2026; Middle East oil flows assumed constrained through the fourth quarter of 2026). EIA, Washington. Observation year 2026. Accessed 2026-11-03.back
- 11UNVERIFIED, not opened: IEA (ed.), Oil Market Report, September 2026; flows through the strait of 7.6 mb/d in August, 2026 supply 100.7 mb/d and demand 102.5 mb/d, and taken from search-result summaries. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 3IEA (ed.), Global Critical Minerals Outlook 2026 (revised version, July 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 4IEA (ed.), Energy and AI (World Energy Outlook Special Report). International Energy Agency, Paris, April 2025. Observation year 2024. Accessed 2026-11-03.back
- Global Energy 2026
- Chapter 8
Systems in depth
One section per system: its state at evidence close, its exposures and what the operational series will watch.
8.1Energy and water
Energy uses water and water uses energy. Hydropower and thermal cooling make power supply sensitive to drought and heat; pumping, treatment and desalination make water supply sensitive to power.
| Component | State | Evidence | Status |
|---|---|---|---|
| Hydropower | output follows river flows; strong hydro and an early monsoon cut fossil generation in India in 2025 | 72 | Reported |
| Thermal cooling | curtailment risk in heat and low flows; volumes not consolidated here | 2 | Inferred |
| Water for compute | cooling demand rising; volumes not consolidated | 4 | Expert input |
| Energy for water | pumping, treatment and desalination add load | 6 | Inferred |
Couplings
- WAT → ENE hydro and cooling
- ENE → WAT pumping and desalination
- AIC → WAT data-centre cooling
Evidence to bind in 2027
- energy-sector water use by region
- hydro exposure to multi-year drought
Related editions
- GLB Global Systems
- GS-01 Water
- GS-03 Food and Agrifood Systems
- GS-04 Health and One Health
- GS-11 Biodiversity and Ecosystems
- SR-02 Critical Infrastructure and Lifeline Systems
8.2Energy and food
Food depends on energy for fertiliser, irrigation, processing and cold chains. The 2026 Hormuz disruption showed that the link runs through sulphur and acid as well as fuel.
| Component | State | Evidence | Status |
|---|---|---|---|
| Fertiliser inputs | sulphur and sulphuric acid supply disrupted; Chinese acid export curbs from May 2026 | 3 | Reported |
| Fuel costs | higher oil and gas prices pass through to farms | 47 | Inferred |
| Cold chains | depend on reliable power; no consolidated series here | 8 | Expert input |
| Bioenergy | competes with food for land | 6 | Inferred |
Couplings
- ENE → FOO fuel and fertiliser
- MIN → FOO acid and sulphur
- TRD → ENE → FOO price transmission
Evidence to bind in 2027
- fertiliser price pass-through by region
- cold-chain power reliability
Related editions
- GLB Global Systems
- GS-01 Water
- GS-03 Food and Agrifood Systems
- GS-04 Health and One Health
- GS-11 Biodiversity and Ecosystems
- SR-02 Critical Infrastructure and Lifeline Systems
8.3Energy and health
Energy access shapes health: clean cooking, clinic power, cooling and refrigeration. Outages and heat make the link visible.
| Component | State | Evidence | Status |
|---|---|---|---|
| Electricity access | 92% of people; 86% of the unserved are in Sub-Saharan Africa | 8 | Reported |
| Clean cooking | 75% have access; 1.8 billion projected to lack it in 2030 | 8 | Reported |
| Cooling demand | lower cooling demand cut growth in 2025 in India and Southeast Asia | 2 | Reported |
| Clinic power | not consolidated here | 8 | Expert input |
Couplings
- ENE → HLT access and cooking
- CLI → ENE → HLT heat and outage
- AIC → ENE → HLT local grid load
Evidence to bind in 2027
- power reliability in health facilities
- heat-wave effects on supply
Related editions
- GLB Global Systems
- GS-01 Water
- GS-03 Food and Agrifood Systems
- GS-04 Health and One Health
- GS-11 Biodiversity and Ecosystems
- SR-02 Critical Infrastructure and Lifeline Systems
8.4Energy and nature
Energy transitions need minerals, land and water, and energy emissions still press on climate. Nature is the unmeasured side of the energy ledger in this edition.
| Component | State | Evidence | Status |
|---|---|---|---|
| Emissions | record above 38 Gt in 2025, up about 0.4% | 2 | Reported |
| Mining | copper, lithium, cobalt and rare-earth supply growing; effects on land and water not consolidated | 3 | Expert input |
| Hydropower | alters river flows; not consolidated here | 15 | Inferred |
| Mitigation pathways | assessed in the IPCC literature | 19 | Inferred |
Couplings
- ENE → BIO mining and land
- ENE → CLI emissions
- MIN → BIO extraction
Evidence to bind in 2027
- ecosystem effects of mineral extraction
- land use of energy supply
Related editions
- GLB Global Systems
- GS-01 Water
- GS-03 Food and Agrifood Systems
- GS-04 Health and One Health
- GS-11 Biodiversity and Ecosystems
- SR-02 Critical Infrastructure and Lifeline Systems
8.5Energy security, grids and extremes
Security of supply now spans fuels, minerals and grids. Chokepoints, concentrated refining and voltage control failures are the three channels the 2025 and 2026 evidence shows.
| Component | State | Evidence | Status |
|---|---|---|---|
| Fuel chokepoints | Hormuz flows cut from March 2026; EIA assumes constraint through the fourth quarter | 4711 | Reported |
| LNG | Ras Laffan offline since early March 2026 | 13 | Reported |
| Minerals | refining concentration rising; export controls tripled in scope | 3 | Reported |
| Grid stability | blackout from interacting factors | 9 | Reported |
Couplings
- TRD → ENE chokepoints
- MIN → ENE equipment
- INF → ENE grid stability
Evidence to bind in 2027
- fuel-market position after evidence close
- grid equipment lead times
Related editions
- GLB Global Systems
- GS-01 Water
- GS-03 Food and Agrifood Systems
- GS-04 Health and One Health
- GS-11 Biodiversity and Ecosystems
- SR-02 Critical Infrastructure and Lifeline Systems
Notes
Numbers are the edition’s reference numbers, so a note reads the same in every chapter. The full list, with every source and its licence, is in Annex C. Annex C, references
- 2IEA (ed.), Global Energy Review 2026 (revised version, May 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 15UNVERIFIED, not opened: Energy Institute (ed.), Statistical Review of World Energy 2026 (75th edition; fossil fuels about 86% of primary energy, hydropower 2.7%, electricity demand up 3%); values taken from a trade-press summary that was opened, not from the Review. Energy Institute, London. Observation year 2025. Accessed 2026-11-03.back
- 4IEA (ed.), Energy and AI (World Energy Outlook Special Report). International Energy Agency, Paris, April 2025. Observation year 2024. Accessed 2026-11-03.back
- 7Ember (ed.), Global Electricity Review 2026: 2025 in review (generation, demand, solar, coal). Ember, London. Observation year 2025. Accessed 2026-11-03.back
- 6IEA (ed.), World Energy Outlook 2025, launch presentation, Paris, 12 November 2025. International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 3IEA (ed.), Global Critical Minerals Outlook 2026 (revised version, July 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 47US Energy Information Administration (ed.), Short-Term Energy Outlook, September 2026 (Brent about USD 91 a barrel in the fourth quarter of 2026; Middle East oil flows assumed constrained through the fourth quarter of 2026). EIA, Washington. Observation year 2026. Accessed 2026-11-03.back
- 8UN DESA Statistics Division (ed.), The Sustainable Development Goals Extended Report 2026, Goal 7 indicator storylines (inputs as of 30 April 2026). United Nations, New York. Observation year 2024. Accessed 2026-11-03.back
- 19UNVERIFIED, not opened: Shukla, P.R. et al. (eds.), Climate Change 2022: Mitigation of Climate Change, Contribution of Working Group III to the Sixth Assessment Report. IPCC, Geneva, 2022. Observation year 2022. Accessed 2026-11-03.back
- 12UNVERIFIED, not opened: IEA (ed.), collective action on emergency oil stocks agreed on 11 March 2026 (400 million barrels, the largest release in the agency’s history), with export volumes through the strait below 10% of pre-conflict levels and pre-war flows of about 20 mb/d, taken from search-result summaries; the release itself is also noted in the opened minerals outlook [3]. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 9ENTSO-E (ed.), 28 April 2025 Iberian blackout: final report of the expert panel (publication page; report dated 20 March 2026). ENTSO-E, Brussels. Observation year 2025. Accessed 2026-11-03.back
- 11UNVERIFIED, not opened: IEA (ed.), Oil Market Report, September 2026; flows through the strait of 7.6 mb/d in August, 2026 supply 100.7 mb/d and demand 102.5 mb/d, and taken from search-result summaries. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 13UNVERIFIED, not opened: IEA (ed.), Gas Market Report, Q2-2026; Ras Laffan offline since early March 2026 and nearly a fifth of global LNG supply removed, taken from search-result summaries. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- Global Energy 2026
- Annex A
Methodology
How the edition was made: methods, the model card, the evidence cut and its age, the acceptance record and the glossary.
A.1Methods
The global baseline uses published values and four simple derivations. Each is shown in full so that any reader can reproduce it.
| No. | Derivation | Calculation | Result |
|---|---|---|---|
| (1) | Electricity growth against energy growth, 2025 | ≈3 ÷ 1.3 | ≈2.3 times |
| (2) | Share of 2025 growth in energy demand from solar (lower bound) | reported as more than 25% | more than 25% |
| (3) | Renewables lead over coal in generation, 2025 | 10,730 − 10,476 TWh | 254 TWh |
| (4) | Growth in data-centre electricity, 2024 to 2030, base case | 945 ÷ 415 | ≈2.3 times |
| Strength | Definition |
|---|---|
| STRONG | a disruption in the source system has historically changed the target system’s service or output within one season, in more than one region |
| MODERATE | an effect is documented but buffered or slower |
| WEAK | an effect is plausible but not documented at global scale |
| Label | Rule |
|---|---|
| Reported | value as issued by its source, with year |
| Inferred | reasoned from cited evidence; never a measurement |
| Estimated | Nexus analytical value with stated method |
| Scenario | conditional on stated assumptions |
| Expert input | structured editorial judgement awaiting evidence |
A.2Model card, Energy Sector Model v0
- Model ID
- MDL-GS02-ENERGY · v0.1
- Purpose
- represent the global energy system and its couplings to water, food, health and biodiversity
- Family
- graph-based system of systems
- Inputs
- the cited sources of this edition; no proprietary data
- Method
- expert-specified coupling strengths (STRONG · MODERATE · WEAK) from assessments and analogue events
- Validation
- none yet, first validation against federation evidence in 2027
- Uncertainty
- qualitative; strengths are hypotheses, not measurements
- Domain of validity
- global scale; not for asset-, site- or country-level use
- Reproducibility
- strength table and sources published in this edition
typed in v0
documented within one season
documented, buffered
plausible, undocumented
A.3The baseline evidence cut
Every Nexus edition is published from a frozen evidence cut. The global baseline cut is documentary: it pins the exact edition of every source cited. Federation cuts begin with the first national Foundry cuts in 2027.
- Cut ID
- DC-SECTOR-ENERGY-GLOBAL-2026-B0
- Type
- baseline documentary cut
- Resolution policy
- pinned · as of 30 September 2026
- Sources pinned
- 47 cited sources, each at the edition and access date in the references
- Model runs
- none at baseline, analytical values are stated with their method
- Digest
- computed at freeze and recorded in the publication record
- Supersedes
- nothing, first cut of the series
- Superseded by
- the 2027 energy annual cut
Lineage
- 01
source edition
- 02
pinned citation
- 03
finding
- 04
page
- 05
publication record
| Element | Baseline 2026 | 2027 global annual |
|---|---|---|
| Sources | cited global publications, pinned by edition | national, regional and sector cuts through one graph |
| Analysis | stated methods and editorial estimates | typed analysis specifications |
| Models | Energy Sector Model v0 specification | model runs with receipts |
| Findings | twelve baseline findings | findings re-bound to federation evidence |
| Review | five passes scheduled | five passes on the exact digest |
A.4Evidence age and coverage
A 2026 global edition rests on evidence observed in many different years. This page shows each time base, so that no single year label hides older evidence.
| Indicator | Observed | Released | Cadence | Next release |
|---|---|---|---|---|
| Energy demand and emissions | 2025 | May 2026 revised | annual | next Global Energy Review |
| Electricity generation shares | 2025 | 2026 | annual | next Electricity Review |
| Investment estimate | 2026e | May 2026 | annual | next investment report |
| Access to electricity and cooking | 2024 | 2026 | annual | next SDG 7 report |
| Data-centre electricity | 2024 | 2025 | one-off | next IEA update |
| Hormuz oil flows | 2026 | Sep 2026 | monthly | monthly |
| LNG capacity and outage | 2025 to 2026 | Q4 2025 and Q2 2026 | quarterly | next Gas Market Report |
| Critical minerals refining | 2025 | revised Jul 2026 | annual | 2027 |
| Primary energy | 2025 | Jun 2026 | annual | 2027 |
| Iberian blackout causes | 2025 | Mar 2026 | one-off | follow-up reports |
| System | Coverage | Thinnest dimension |
|---|---|---|
| Demand and supply | GOOD | regional drivers of growth |
| Electricity | GOOD | grid-level constraints |
| Fuel markets | PARTIAL | position after evidence close |
| Minerals | GOOD | equipment-level dependence |
| Access | GOOD | service quality and affordability |
| Investment | PARTIAL | split by technology and region |
| Water for energy | THIN | volumes by region and technology |
| Resilience | PARTIAL | tested capabilities beyond oil stocks |
| Field | Source that would fill it | Blocker |
|---|---|---|
| Fuel-market position on 1 November 2026 | IEA Oil Market Report for October and November 202611; EIA Short-Term Energy Outlook of November | releases after the evidence close and not retrieved; the EIA September outlook47 is the baseline source; the October outlook10 is post-close, context only |
| Hormuz flow volumes before and during the conflict, from a primary document | IEA Oil Market Reports1112 | the report was not opened; only search summaries were read |
| Clean and fossil split of the 2026 investment estimate | IEA World Energy Investment 2026 full report17 | report page not accessible; the launch presentation was opened without the split |
| Capacity added in 2025, on one basis | IEA, IRENA and Ember series2147 | the series use different methods; not reconciled in this edition |
| Transformer, cable and interconnection-queue constraints | IEA grids work22; national operators | not retrieved; figures in memory are not used |
| Energy-sector water use by region | IEA and national statistics offices | no consolidated global series found at evidence close |
| Heat-wave effects on power systems in 2026 | operator reports; weather services | not retrieved |
| Cyber and physical incidents on energy infrastructure | operators and national authorities | incident data are not published on a common basis |
| Winter gas storage at the start of the heating season | Gas Infrastructure Europe; operators | not retrieved |
| Energy support for poor households, by country | national ministries; World Bank | not consolidated; capability rung stays LISTED |
| Energy employment and skills gap | IEA World Energy Employment 202523 | report not opened; no figure used |
| Data-centre electricity by country after 2024 | IEA, national regulators, operators | later series use a different baseline; not mixed with the 415 TWh figure |
| Capability rungs beyond emergency stocks | operators, regulators, ministries | not reviewed |
A.5Evidence cards, two anchor sources
Issued by the International Energy Agency (revised May 2026) from energy balances, market data and technology tracking. Annual. Role: binds ENE-001, ENE-002 and CLI-004.
EVD-GS02-001
IEA Global Energy Review 20262
Compiled by UN DESA from custodian storylines as of 30 April 2026. Annual. Role: binds HLT-007 and the access tiles. Figures differ slightly from the main report text.
EVD-GS02-002
SDG 7 Extended Report 20268
| Dimension | EVD-GS02-001 | EVD-GS02-002 |
|---|---|---|
| Completeness | all fuels and technologies; modelled where national data are missing | country coverage uneven; cooking estimate is a range |
| Timeliness | about 5 months after the year | about 16 months after the year |
| Revision | revised version issued May 2026 | storylines updated up to the report date |
| Method transparency | methodology published | indicator metadata published |
| External validation | compared with national statistics | custodian review |
Evidence cards to follow in 2027
A.6Publication acceptance record
Editorial self-check at evidence close. Every applicable item carries a disposition; the remaining items are review, approval and deposit.
| Group | Area | Items | Pass | N/A | Pending |
|---|---|---|---|---|---|
| D1 | Identity and scope | 8 | 8 | 0 | 0 |
| D2 | Source and data | 12 | 9 | 1 | 2 |
| D3 | Analysis and models | 12 | 3 | 8 | 1 |
| D4 | Findings and claims | 9 | 8 | 0 | 1 |
| D5 | Figures, tables, maps | 10 | 6 | 2 | 2 |
| D6 | Editorial and citations | 10 | 8 | 0 | 2 |
| D7 | Review and approval | 13 | 0 | 0 | 13 |
| D8 | Artefact and design | 12 | 7 | 0 | 5 |
| D9 | Registry and release | 9 | 0 | 0 | 9 |
Publication gate
- Conditions met
- 14 of 23 at evidence close
- Blocking problems
- none recorded
- Open conditions
- reviews, approval of the exact digest, deposit, registry pointer
Not applicable at baseline
- Model runs
- first runs in Q1 2027
- Maps
- plates in Q2 2027
- Waivers
- none
A.7Status words
| Status | What it means |
|---|---|
| Observed | Measured directly and published by the source. |
| Reported | Published statistics of an official or institutional source. |
| Declared | Stated by the body concerned; not independently measured. |
| Estimated | A Nexus estimate from cited evidence, with its method in Annex A. |
| Modelled | Produced by a stated model from cited inputs. |
| Inferred | Reasoned from cited evidence; not measured. |
| Forecast | A projection by the cited source. |
| Simulated | A simulation result under stated assumptions. |
| Scenario | A conditional statement under stated assumptions; never a prediction. |
| Expert input | Expert judgement, recorded with its basis. |
| Candidate | Proposed for a later edition; not yet evidence. |
| Evidence-quality levels (EQL 1 to 5) grade the source behind a value; they are not a score of the subject. | |
A.8How the edition is made, released and corrected
Every edition is built from a sealed evidence cut, reviewed under three keys, signed and deposited before any site shows it as published; corrections go to Nexus Standards as change proposals and feed the next cut.
| Step | What happens | Source |
|---|---|---|
| 01 Evidence arrives from the pillars | Foundry seals observations and indicator series, Universe hands over after-action and scenario findings, and contributions are screened at every gateway, including this site’s. | |
| 02 The cut is sealed | On the cut date the evidence is pinned under one identifier, so anyone can rebuild the edition from exactly what it was built on. | |
| 03 The edition is assembled | The edition is drafted from its template and content pack. Agents may draft; they never publish and never decide. | |
| 04 The keys turn | At the publisher of record the truth key comes first: every value is checked against its source or stated method before the meaning and capital keys turn. No edition moves on until every key has been turned by a named steward. | |
| 05 The gate opens | A named approver releases one exact digest of the edition; any change after this point is a new version, never a silent edit. | |
| 06 Signed and deposited | The PDF, the web edition and the data bundle are signed together with a manifest and an RO-Crate description, and deposited on Zenodo with a concept and a version DOI. | |
| 07 Published on its desk’s site | Only then does the edition show as published on its desk’s Reports site, and the Collection lists it as a part. | |
| 08 Corrections go to Standards | Method and correction findings go to Nexus Standards as change proposals; citations, corrections and new contributions feed the next evidence cut. |
A teaching model of the process, not a forecast and not a record of any run; dates and counts on this page come from the programme record. Sources: Reports governance at GCRI Canada (2026); Zenodo, repository of record for Reports deposits (2026).
Lifecycle, one state at a time: Draft, Computed, Evidence bound, Reviewed, Approved for release, Published, Corrected, Superseded. This edition is a draft.
A.9Glossary and abbreviations
| Term | Meaning |
|---|---|
| Baseline Edition | the inaugural annual edition that fixes the reference state for the series |
| WEFH+B | energy, energy, food, health and biodiversity, the national nexus core |
| Coupling | a typed dependency through which one system transmits to another |
| Protection gap | the share of losses not covered by insurance |
| Capability ladder | LISTED → EXISTS → ADEQUATE → TESTED → DEMONSTRATED |
| EQL | evidence-quality level, 1–5 |
| Evidence cut | a frozen resolution of exact sources and versions |
| NNC · NLC · NWG | National Nexus Consortium · National Leadership Council · National Working Groups |
| Abbreviation | Expansion |
|---|---|
| bcm | billion cubic metres |
| EJ | exajoule |
| ENTSO-E | European Network of Transmission System Operators for Electricity |
| GW | gigawatt |
| IEA | International Energy Agency |
| IRENA | International Renewable Energy Agency |
| LNG | liquefied natural gas |
| Mtpa | million tonnes per annum |
| SDG 7 | Sustainable Development Goal 7: affordable and clean energy |
| STEO | Short-Term Energy Outlook |
| TWh | terawatt-hour |
| TFEC | total final energy consumption |
A.10Technical annex
| Item | Annex | Contents | Status |
|---|---|---|---|
| A.1 | Indicator definitions | the global indicator set, with units and sources | IN THIS EDITION |
| A.2 | Coupling strengths | the twenty-cell matrix and its rationale | IN THIS EDITION |
| A.3 | Scenario specification | SCN-GS02-LNG-01 assumptions and signposts | IN THIS EDITION |
| A.4 | Capability placements | rung evidence for fifteen functions | IN THIS EDITION |
| A.5 | Model diagnostics | first runs and validation | 2027 |
| A.6 | Sensitivity analyses | influence of coupling strengths | 2027 |
| A.7 | Grid and route notes | cards for the major shared grids and fuel routes | WITH REGIONAL EDITIONS |
| A.8 | Review statements | pass-by-pass review record | AT RELEASE |
A.1 · indicator definition: access to electricity
- Construct
- share and number of people living in households with access to electricity
- Unit
- share and number of people
- Method
- custodian indicator based on national surveys and models
- Source
- SDG 7 Extended Report 20268
- Uncertainty
- modelled where survey data are missing
- Known limits
- binary measure; does not capture reliability, capacity or affordability
Notes
Numbers are the edition’s reference numbers, so a note reads the same in every chapter. The full list, with every source and its licence, is in Annex C. Annex C, references
- 11UNVERIFIED, not opened: IEA (ed.), Oil Market Report, September 2026; flows through the strait of 7.6 mb/d in August, 2026 supply 100.7 mb/d and demand 102.5 mb/d, and taken from search-result summaries. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 47US Energy Information Administration (ed.), Short-Term Energy Outlook, September 2026 (Brent about USD 91 a barrel in the fourth quarter of 2026; Middle East oil flows assumed constrained through the fourth quarter of 2026). EIA, Washington. Observation year 2026. Accessed 2026-11-03.back
- 10POST-CLOSE, context only: US Energy Information Administration (ed.), Short-Term Energy Outlook, October 2026 (released 6 October 2026, after the 30 September evidence close; post-close, context only, supports no baseline claim). EIA, Washington. Observation year 2026. Accessed 2026-11-03.back
- 12UNVERIFIED, not opened: IEA (ed.), collective action on emergency oil stocks agreed on 11 March 2026 (400 million barrels, the largest release in the agency’s history), with export volumes through the strait below 10% of pre-conflict levels and pre-war flows of about 20 mb/d, taken from search-result summaries; the release itself is also noted in the opened minerals outlook [3]. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 17UNVERIFIED, not opened: IEA (ed.), World Energy Investment 2026, full report (clean energy about USD 2.2 trillion and fossil fuels about USD 1.2 trillion in search summaries). International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- 2IEA (ed.), Global Energy Review 2026 (revised version, May 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 14UNVERIFIED, not opened: IRENA (ed.), Renewable Capacity Statistics 2026 (about 692 GW added in 2025; 5,149 GW total), taken from search-result summaries; the page returned an access error. International Renewable Energy Agency, Abu Dhabi. Observation year 2025. Accessed 2026-11-03.back
- 7Ember (ed.), Global Electricity Review 2026: 2025 in review (generation, demand, solar, coal). Ember, London. Observation year 2025. Accessed 2026-11-03.back
- 22UNVERIFIED, not opened: IEA (ed.), Electricity Grids and Secure Energy Transitions. International Energy Agency, Paris, 2023. Observation year 2023. Accessed 2026-11-03.back
- 23UNVERIFIED, not opened: IEA (ed.), World Energy Employment 2025. International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 8UN DESA Statistics Division (ed.), The Sustainable Development Goals Extended Report 2026, Goal 7 indicator storylines (inputs as of 30 April 2026). United Nations, New York. Observation year 2024. Accessed 2026-11-03.back
- 9ENTSO-E (ed.), 28 April 2025 Iberian blackout: final report of the expert panel (publication page; report dated 20 March 2026). ENTSO-E, Brussels. Observation year 2025. Accessed 2026-11-03.back
- 3IEA (ed.), Global Critical Minerals Outlook 2026 (revised version, July 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 13UNVERIFIED, not opened: IEA (ed.), Gas Market Report, Q2-2026; Ras Laffan offline since early March 2026 and nearly a fifth of global LNG supply removed, taken from search-result summaries. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03.back
- Global Energy 2026
- Annex B
Data appendix
The indicator set with its sources, the source registers, the licences of every kind of material and the formats of the edition.
B.1The indicator set
| Indicator | Value | Unit | Year | State | Source |
|---|---|---|---|---|---|
| Growth in global energy demand | 1.3 | % | 2025 | Reported | 2 |
| Growth in electricity demand | ≈3 | % | 2025 | Reported | 2 |
| Growth in electricity demand (Ember) | 2.8 | % | 2025 | Reported | 7 |
| Solar generation | 2,778 | TWh | 2025 | Reported | 7 |
| Renewables share of generation | 33.8 | % | 2025 | Reported | 7 |
| Coal share of generation | 33.0 | % | 2025 | Reported | 7 |
| Fossil generation change | −38 | TWh | 2025 | Reported | 7 |
| Renewable capacity added (IEA) | 800 | GW | 2025 | Reported | 2 |
| Battery storage added | ≈110 | GW | 2025 | Reported | 2 |
| Energy-related CO2 | >38 | Gt | 2025 | Reported | 2 |
| Global energy investment | 3.4 | USD trillion | 2026e | Reported | 1 |
| Electricity supply and infrastructure investment | 1.6 | USD trillion | 2026e | Reported | 1 |
| Data-centre electricity | 415 | TWh | 2024 | Reported | 4 |
| Data-centre electricity, base case | 945 | TWh | 2030 | Scenario | 4 |
| People without electricity | 655 | million | 2024 | Reported | 8 |
| People cooking with polluting fuels | 2.0 | billion | 2024 | Reported | 8 |
| Top refiner share, key minerals excluding rare earths | 72 | % | 2025 | Reported | 3 |
| Brent, fourth-quarter 2026 (forecast) | 91 | USD a barrel | 2026 | Scenario | 47 |
B.2Global source register
The governed source set behind this edition. Each source keeps its authority, coverage, cadence and role; categories describe origin, not truth.
Domains bound by the register
- ENE
- CLI
- FIN
- HLT
- MIN
- INF
- AIC
- TRD
- WAT
- FOO
| Source | Category | Coverage | Period | Cadence | Role |
|---|---|---|---|---|---|
| IEA Global Energy Review 20262 | intergovernmental agency | global | 2025 | annual | demand, emissions |
| IEA World Energy Investment 20261 | intergovernmental agency | global | 2026e | annual | investment |
| IEA Critical Minerals Outlook 20263 | intergovernmental agency | global | 2025 | annual | minerals |
| IEA Energy and AI4 | intergovernmental agency | global | 2024 | one-off | data centres |
| IEA Gas Market Report5 | intergovernmental agency | global | 2025 | quarterly | gas, LNG |
| Ember Global Electricity Review7 | think tank, open data | global | 2025 | annual | generation |
| SDG 7 Extended Report8 | UN agencies | global | 2024 | annual | access |
| ENTSO-E blackout report9 | operators’ association | Continental Europe | 2025 | one-off | grid failure |
| EIA Short-Term Energy Outlook47 | national statistics agency | US and global | 2026 | monthly | prices, flows |
| EIA Short-Term Energy Outlook, October 202610 | national statistics agency | US and global | 2026 | monthly | post-close, context only |
| IRENA capacity statistics14 | intergovernmental agency | global | 2025 | annual | capacity |
B.3Regional reading: energy across ten clusters
Map plates follow with the regional Baseline Editions, when boundary sources and public-safe resolutions are bound. This page gives the regional reading in table form and ranks no region.
| Region | Principal hazards | Systems most exposed | Baseline evidence |
|---|---|---|---|
| North America | data-centre load; winter cold; gas-to-coal switching | power, gas, industry | US energy demand and coal use2 |
| South America | hydropower dependence in dry years | power, cities | regional statistics (not bound) |
| Europe | gas import dependence; grid stability | power, heating, industry | blackout report9; solar and wind 30% of EU generation2 |
| Eurasia | export flows and sanctions | gas, oil | IEA gas report5 |
| Middle East and North Africa | Hormuz and LNG exposure | oil, gas, aluminium, sulphur | minerals outlook3; EIA47 |
| Africa | access gaps; clean cooking | households, health | SDG 78 |
| South Asia | import dependence; monsoon and heat | power, fertiliser | IEA Global Energy Review2 |
| East Asia | LNG and oil import dependence; clean-tech supply | power, industry | critical minerals3 |
| ASEAN | rising demand; LNG imports | power, cities | IEA gas report5 |
| Oceania-Pacific | small island fuel imports; export minerals | power, ports | regional statistics (not bound) |
B.4Grid card: Continental Europe synchronous area
- grid
- synchronous
- interconnected
- cross-border
- Systems in view
- power, heating, industry, cities
- Defining events
- blackout in Spain and Portugal on 28 April 20259
- Couplings
- ENE → HLT outages; ENE → INF voltage; ENE → FIN prices
- Capability evidence
- restoration and a published expert final report9
- Gaps
- cross-border flow detail; reactive power coverage
- Agenda items
- E-01 · E-02
The final report names gaps in voltage and reactive power control and differences in practice across areas as interacting factors [9].
GRID
Voltage control
A synchronous grid shares its stability across borders, so a local failure can propagate.
SECURITY
Interdependence
The report is an expert analysis of causes and recommendations, not an attribution of liability [9].
LEARNING
Public final report
B.5How countries appear in the energy edition
Countries enter the energy edition through the energy chapters of their own national editions, on one card grammar. They are read against peer distributions and thresholds, never ranked.
| Card field | What it shows | Source |
|---|---|---|
| WEFH+B state | each core system against peer distribution bands | national edition |
| Couplings | the national dependency matrix | national edition |
| Risk objects | the national risk portfolio | national edition |
| Capability rungs | the national capability ladder | national edition |
| Evidence age | oldest and newest source dates | national source register |
Editions in the 2026 Baseline programme
countries and unions
clusters
flagship and sector
technology reports
How to read a country card
- Each system is shown against the distribution of its peers, with thresholds where they exist
- Couplings and risk objects come from the country’s own national edition
- Capability rungs record evidence, not a judgement of institutions
- Evidence age is printed, so older national data are visible as such
| Wave | Countries and unions | State |
|---|---|---|
| W0 | Canada | ISSUED |
| W1 | United States, United Kingdom, France, Germany, Italy, Japan, European Union, Switzerland | PLANNED |
| W2 | Mexico, Brazil, Argentina, Türkiye, Russian Federation, Saudi Arabia, United Arab Emirates, South Africa, Senegal, Kenya, African Union, India, China, Republic of Korea, Indonesia, Singapore, Australia | PLANNED |
B.6Licences
| Material | Licence |
|---|---|
| Text | CC BY 4.0 |
| Data | on the licence of each source; Nexus tables CC BY 4.0 |
| Figures | Nexus figures CC BY 4.0; third-party as credited |
| Maps | boundary source and licence printed on each plate |
| Metadata | CC0 1.0, as Zenodo publishes it |
| Third-party data, figures and text | The source’s own licence, credited where it is used; never relicensed |
| Nexus-authored text, tables and figures: CC BY 4.0 (SPDX CC-BY-4.0). Map plates print their boundary source and licence. | |
B.7Formats and provenance
| Format | Kind | State | What it is | Identifier |
|---|---|---|---|---|
| Web edition | HTML | On this site | Draft in stewardship review; every value resolves to its source. | NR-SECTOR-ENERGY-GLOBAL-2026-BASELINE-v1.0.0 |
| Print edition | At release | A4 portrait · screen, print and archival PDF, signed with the web edition at release. | NR-SECTOR-ENERGY-GLOBAL-2026-BASELINE-v1.0.0 | |
| Indicator data | CSV · JSON | On this site | 18 indicators with unit, year, status and source; the machine-readable copy ships with the evidence bundle at release. | NR-SECTOR-ENERGY-GLOBAL-2026-BASELINE data release v1 |
| Figures | SVG · PNG | On this site | 4 on the web edition: headline figure, figure 1.3, coupling instrument, capability ladder. | FIG-SECTOR-ENERGY-GLOBAL-2026-BASELINE-* |
| Slides | Not recorded | No slide deck is recorded for this edition. | ||
| Evidence brief | HTML · PDF | Not recorded | No evidence brief is recorded for this edition. | |
| Dataset with DOI | DataCite | At release | Concept and version DOI are minted at deposit; none is recorded yet. |
Provenance
- Edition pack
- The edition’s content pack (JSON), from which the print and web editions are built
- Evidence cut
- DC-SECTOR-ENERGY-GLOBAL-2026-B0, closed 30 September 2026
- Reproducibility
- sourced values cited; analytical values reproducible from stated parameters
- Self-check
- 14 of 23 at evidence close; a fail on any item blocks release
- Review
- five passes scheduled before release (in Annex C)
- Publisher of record
- GCRI for the Nexus Consortium
- Corrections
- Registry correction pathway; upheld corrections are published as notices with a new version
Notes
Numbers are the edition’s reference numbers, so a note reads the same in every chapter. The full list, with every source and its licence, is in Annex C. Annex C, references
- 2IEA (ed.), Global Energy Review 2026 (revised version, May 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 7Ember (ed.), Global Electricity Review 2026: 2025 in review (generation, demand, solar, coal). Ember, London. Observation year 2025. Accessed 2026-11-03.back
- 1IEA (ed.), World Energy Investment 2026, launch presentation, Paris, 28 May 2026. International Energy Agency, Paris. Observation year 2026 (estimates, with 2025 data). Accessed 2026-11-03.back
- 4IEA (ed.), Energy and AI (World Energy Outlook Special Report). International Energy Agency, Paris, April 2025. Observation year 2024. Accessed 2026-11-03.back
- 8UN DESA Statistics Division (ed.), The Sustainable Development Goals Extended Report 2026, Goal 7 indicator storylines (inputs as of 30 April 2026). United Nations, New York. Observation year 2024. Accessed 2026-11-03.back
- 3IEA (ed.), Global Critical Minerals Outlook 2026 (revised version, July 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 47US Energy Information Administration (ed.), Short-Term Energy Outlook, September 2026 (Brent about USD 91 a barrel in the fourth quarter of 2026; Middle East oil flows assumed constrained through the fourth quarter of 2026). EIA, Washington. Observation year 2026. Accessed 2026-11-03.back
- 15UNVERIFIED, not opened: Energy Institute (ed.), Statistical Review of World Energy 2026 (75th edition; fossil fuels about 86% of primary energy, hydropower 2.7%, electricity demand up 3%); values taken from a trade-press summary that was opened, not from the Review. Energy Institute, London. Observation year 2025. Accessed 2026-11-03.back
- 5IEA (ed.), Gas 2025: Analysis and forecasts to 2030 (Gas Market Report, Q4-2025). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03.back
- 9ENTSO-E (ed.), 28 April 2025 Iberian blackout: final report of the expert panel (publication page; report dated 20 March 2026). ENTSO-E, Brussels. Observation year 2025. Accessed 2026-11-03.back
- 10POST-CLOSE, context only: US Energy Information Administration (ed.), Short-Term Energy Outlook, October 2026 (released 6 October 2026, after the 30 September evidence close; post-close, context only, supports no baseline claim). EIA, Washington. Observation year 2026. Accessed 2026-11-03.back
- 14UNVERIFIED, not opened: IRENA (ed.), Renewable Capacity Statistics 2026 (about 692 GW added in 2025; 5,149 GW total), taken from search-result summaries; the page returned an access error. International Renewable Energy Agency, Abu Dhabi. Observation year 2025. Accessed 2026-11-03.back
- Global Energy 2026
- Annex C
References and record
Every source the edition rests on, the publication record, the corrections log and the open record.
C.147 sources
NR-CIT-1, editor first. A DOI is linked where the source has one; Nexus records carry a UNI once the catalogue allocates it (NS-1).
- 1IEA (ed.), World Energy Investment 2026, launch presentation, Paris, 28 May 2026. International Energy Agency, Paris. Observation year 2026 (estimates, with 2025 data). Accessed 2026-11-03. Cited in the summary, chapter 2, chapter 3, chapter 4, chapter 6
- 2IEA (ed.), Global Energy Review 2026 (revised version, May 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03. Cited in the summary, chapter 1, chapter 2, chapter 3, chapter 4, chapter 6, chapter 8
- 3IEA (ed.), Global Critical Minerals Outlook 2026 (revised version, July 2026). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03. Cited in the summary, chapter 1, chapter 2, chapter 3, chapter 4, chapter 6, chapter 7, chapter 8
- 4IEA (ed.), Energy and AI (World Energy Outlook Special Report). International Energy Agency, Paris, April 2025. Observation year 2024. Accessed 2026-11-03. Cited in the summary, chapter 1, chapter 2, chapter 4, chapter 6, chapter 7, chapter 8
- 5IEA (ed.), Gas 2025: Analysis and forecasts to 2030 (Gas Market Report, Q4-2025). International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03. Cited in chapter 2, chapter 6
- 6IEA (ed.), World Energy Outlook 2025, launch presentation, Paris, 12 November 2025. International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03. Cited in chapter 6, chapter 8
- 7Ember (ed.), Global Electricity Review 2026: 2025 in review (generation, demand, solar, coal). Ember, London. Observation year 2025. Accessed 2026-11-03. Cited in the summary, chapter 1, chapter 2, chapter 3, chapter 4, chapter 6, chapter 8
- 8UN DESA Statistics Division (ed.), The Sustainable Development Goals Extended Report 2026, Goal 7 indicator storylines (inputs as of 30 April 2026). United Nations, New York. Observation year 2024. Accessed 2026-11-03. Cited in the summary, chapter 1, chapter 2, chapter 3, chapter 6, chapter 8
- 9ENTSO-E (ed.), 28 April 2025 Iberian blackout: final report of the expert panel (publication page; report dated 20 March 2026). ENTSO-E, Brussels. Observation year 2025. Accessed 2026-11-03. Cited in chapter 1, chapter 2, chapter 3, chapter 4, chapter 6, chapter 8
- 10POST-CLOSE, context only: US Energy Information Administration (ed.), Short-Term Energy Outlook, October 2026 (released 6 October 2026, after the 30 September evidence close; post-close, context only, supports no baseline claim). EIA, Washington. Observation year 2026. Accessed 2026-11-03.
- 11UNVERIFIED, not opened: IEA (ed.), Oil Market Report, September 2026; flows through the strait of 7.6 mb/d in August, 2026 supply 100.7 mb/d and demand 102.5 mb/d, and taken from search-result summaries. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03. Cited in the summary, chapter 1, chapter 2, chapter 4, chapter 5, chapter 6, chapter 7, chapter 8
- 12UNVERIFIED, not opened: IEA (ed.), collective action on emergency oil stocks agreed on 11 March 2026 (400 million barrels, the largest release in the agency’s history), with export volumes through the strait below 10% of pre-conflict levels and pre-war flows of about 20 mb/d, taken from search-result summaries; the release itself is also noted in the opened minerals outlook [3]. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03. Cited in the summary, chapter 1, chapter 2, chapter 4, chapter 6, chapter 8
- 13UNVERIFIED, not opened: IEA (ed.), Gas Market Report, Q2-2026; Ras Laffan offline since early March 2026 and nearly a fifth of global LNG supply removed, taken from search-result summaries. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03. Cited in chapter 1, chapter 2, chapter 4, chapter 6, chapter 8
- 14UNVERIFIED, not opened: IRENA (ed.), Renewable Capacity Statistics 2026 (about 692 GW added in 2025; 5,149 GW total), taken from search-result summaries; the page returned an access error. International Renewable Energy Agency, Abu Dhabi. Observation year 2025. Accessed 2026-11-03. Cited in chapter 6
- 15UNVERIFIED, not opened: Energy Institute (ed.), Statistical Review of World Energy 2026 (75th edition; fossil fuels about 86% of primary energy, hydropower 2.7%, electricity demand up 3%); values taken from a trade-press summary that was opened, not from the Review. Energy Institute, London. Observation year 2025. Accessed 2026-11-03. Cited in chapter 1, chapter 2, chapter 6, chapter 8
- 16UNVERIFIED, not opened: IEA (ed.), Electricity Mid-Year Update 2026 (23 July 2026; demand growth 3.6% in 2026 and 3.8% in 2027 in search summaries); no figure from it is used in a finding. International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03. Cited in chapter 6
- 17UNVERIFIED, not opened: IEA (ed.), World Energy Investment 2026, full report (clean energy about USD 2.2 trillion and fossil fuels about USD 1.2 trillion in search summaries). International Energy Agency, Paris. Observation year 2026. Accessed 2026-11-03. Cited in chapter 2
- 18UNVERIFIED, not opened: Shehabi, A. et al., 2024 United States Data Center Energy Usage Report, Lawrence Berkeley National Laboratory, Berkeley, December 2024; the page returned an access error and no figure is used. Observation year 2023. Accessed 2026-11-03. Cited in chapter 6
- 19UNVERIFIED, not opened: Shukla, P.R. et al. (eds.), Climate Change 2022: Mitigation of Climate Change, Contribution of Working Group III to the Sixth Assessment Report. IPCC, Geneva, 2022. Observation year 2022. Accessed 2026-11-03. Cited in chapter 6, chapter 8
- 20UNVERIFIED, not opened: UNFCCC (ed.), Outcome of the first global stocktake, decision 1/CMA.5 (December 2023; tripling renewable capacity and transitioning away from fossil fuels in energy systems), cited from memory. UNFCCC, Bonn. Observation year 2023. Accessed 2026-11-03. Cited in chapter 6
- 21UNVERIFIED, not opened: IEA (ed.), Net Zero Roadmap: A Global Pathway to Keep the 1.5 °C Goal in Reach, 2023 update. International Energy Agency, Paris. Observation year 2023. Accessed 2026-11-03. Cited in chapter 6
- 22UNVERIFIED, not opened: IEA (ed.), Electricity Grids and Secure Energy Transitions. International Energy Agency, Paris, 2023. Observation year 2023. Accessed 2026-11-03. Cited in chapter 4, chapter 6
- 23UNVERIFIED, not opened: IEA (ed.), World Energy Employment 2025. International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03. Cited in chapter 4
- 24UNVERIFIED, not opened: IEA (ed.), Energy Efficiency 2025. International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03. Cited in chapter 4
- 25UNVERIFIED, not opened: IEA (ed.), Oil 2025: Analysis and forecast to 2030. International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03. Cited in chapter 6
- 26UNVERIFIED, not opened: IEA (ed.), Electricity 2025: Analysis and forecast to 2027. International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03. Cited in chapter 6
- 27UNVERIFIED, not opened: IRENA (ed.), World Energy Transitions Outlook 2024. International Renewable Energy Agency, Abu Dhabi. Observation year 2024. Accessed 2026-11-03. Cited in chapter 6
- 28UNVERIFIED, not opened: IRENA (ed.), Tracking COP28 outcomes: tripling renewable power capacity and doubling energy efficiency by 2030. International Renewable Energy Agency, Abu Dhabi, 2024. Observation year 2024. Accessed 2026-11-03. Cited in chapter 6
- 29UNVERIFIED, not opened: IAEA (ed.), Energy, Electricity and Nuclear Power Estimates for the Period up to 2050, 2025 edition. International Atomic Energy Agency, Vienna. Observation year 2025. Accessed 2026-11-03. Cited in chapter 6
- 30UNVERIFIED, not opened: NERC (ed.), Long-Term Reliability Assessment, 2025 edition, North American Electric Reliability Corporation, Atlanta, cited from memory. Observation year 2025. Accessed 2026-11-03. Cited in chapter 4, chapter 6
- 31UNVERIFIED, not opened: UNEP (ed.), Emissions Gap Report 2025. United Nations Environment Programme, Nairobi. Observation year 2025. Accessed 2026-11-03. Cited in chapter 6
- 32UNVERIFIED, not opened: SEI, Climate Analytics, E3G, IISD and UNEP (eds.), The Production Gap Report 2023. Stockholm Environment Institute, Stockholm. Observation year 2023. Accessed 2026-11-03. Cited in chapter 6
- 33UNVERIFIED, not opened: Regulation (EU) 2024/1252 establishing a framework for a secure and sustainable supply of critical raw materials (Critical Raw Materials Act), Official Journal of the European Union, 2024, cited from memory. Observation year 2024. Accessed 2026-11-03. Cited in chapter 6
- 34UNVERIFIED, not opened: Regulation (EU) 2024/1747 amending Regulations (EU) 2019/942 and (EU) 2019/943 on the electricity market design, Official Journal of the European Union, 2024, cited from memory. Observation year 2024. Accessed 2026-11-03. Cited in chapter 3, chapter 6
- 35UNVERIFIED, not opened: Commission Delegated Regulation (EU) 2024/1366 establishing a network code on cybersecurity aspects of cross-border electricity flows, Official Journal of the European Union, 2024, cited from memory. Observation year 2024. Accessed 2026-11-03. Cited in chapter 3, chapter 4, chapter 6
- 36UNVERIFIED, not opened: ISO 50001:2018, Energy management systems: requirements with guidance for use. International Organization for Standardization, Geneva. Observation year 2018. Accessed 2026-11-03. Cited in chapter 4, chapter 6
- 37UNVERIFIED, not opened: IEC 62443 series, Security for industrial automation and control systems. International Electrotechnical Commission, Geneva. Observation year 2018. Accessed 2026-11-03. Cited in chapter 6
- 38UNVERIFIED, not opened: IEA (ed.), Climate Resilience for Energy Security. International Energy Agency, Paris, 2022. Observation year 2022. Accessed 2026-11-03. Cited in chapter 6
- 39UNVERIFIED, not opened: IEA (ed.), Renewables 2025: Analysis and forecasts to 2030. International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03. Cited in chapter 6
- 40UNVERIFIED, not opened: IEA (ed.), Global Hydrogen Review 2025. International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03. Cited in chapter 6
- 41UNVERIFIED, not opened: IEA (ed.), Global Methane Tracker 2025. International Energy Agency, Paris. Observation year 2025. Accessed 2026-11-03. Cited in chapter 6
- 42UNVERIFIED, not opened: IEA (ed.), Energy Technology Perspectives 2024. International Energy Agency, Paris. Observation year 2024. Accessed 2026-11-03. Cited in chapter 6
- 43UNVERIFIED, not opened: Davis, S.J. et al., Net-zero emissions energy systems, Science 360(6396), eaas9793, 2018, cited from memory. American Association for the Advancement of Science. Observation year 2018. Accessed 2026-11-03. Cited in chapter 3, chapter 4, chapter 6
- 44UNVERIFIED, not opened: Creutzig, F. et al., Towards demand-side solutions for mitigating climate change, Nature Climate Change 8, 260 to 263, 2018, cited from memory. Springer Nature. Observation year 2018. Accessed 2026-11-03. Cited in chapter 6
- 45UNVERIFIED, not opened: Ueckerdt, F. et al., Potential and risks of hydrogen-based e-fuels in climate change mitigation, Nature Climate Change 11, 384 to 393, 2021, cited from memory. Springer Nature. Observation year 2021. Accessed 2026-11-03. Cited in chapter 6
- 46UNVERIFIED, not opened: Zscheischler, J. et al., Future climate risk from compound events, Nature Climate Change 8, 469 to 477, 2018, cited from memory. Springer Nature. Observation year 2018. Accessed 2026-11-03. Cited in chapter 6
- 47US Energy Information Administration (ed.), Short-Term Energy Outlook, September 2026 (Brent about USD 91 a barrel in the fourth quarter of 2026; Middle East oil flows assumed constrained through the fourth quarter of 2026). EIA, Washington. Observation year 2026. Accessed 2026-11-03. Cited in the summary, chapter 1, chapter 2, chapter 3, chapter 5, chapter 6, chapter 7, chapter 8
C.2Publication record
Publication
- Title
- Global Energy Risk & Resilience Report 2026: Baseline Edition
- Series
- Reports · Global Sector Series GS-02
- Edition
- Baseline Edition 2026 · inaugural annual
- Version
- v1.0.0 · draft for stewardship review
- Publication ID
- NR-SECTOR-ENERGY-GLOBAL-2026-BASELINE-v1.0.0
- Evidence close
- 30 September 2026
- Publication date
- October 2026
- DOI
- concept and version DOI at deposit
Publisher
- Publisher of record
- The Global Centre for Risk and Innovation (GCRI), for the Nexus Consortium
- Place
- Toronto
- Editor
- Saeed Valadbaygi, Chief Steward and Managing Editor
- Stewards
- GCRI · technical truth · GRF · public meaning · GRA · capital meaning
- Licence
- text CC BY 4.0; data on the terms of each source
- Copyright
- © 2026 GCRI · Nexus Consortium
- Language
- English (en-GB) source edition
- Correspondence
- Registry correction pathway · editorial office
Colophon
- Format
- A4 portrait · screen, print and archival PDF
- Typefaces
- Space Grotesk (display) · Geist (text) · IBM Plex Sans Italic (standfirsts) · IBM Plex Mono (data)
- Design standard
- Reports Foundational Edition, Volume I, Part VII
- Accessibility
- tagged PDF and HTML targets; text alternatives for every figure
- Production
- Reports editorial team, GCRI
Release path for this version
| Step | What happens | When |
|---|---|---|
| Draft | editorial self-check complete at evidence close | October 2026 |
| Steward review | five passes on the exact draft (keys T · M · F · N) | Q4 2026 |
| Approval | publication authority approves the exact digest | before release |
| Deposit | concept and version DOI minted; registry pointer set | at release |
| Succession | the 2027 energy edition reports changes against this baseline | 2027 |
- Current version
- v1.0.0 draft, stewardship review
- Previous edition
- none, first edition of the series
- Next edition
- NR-SECTOR-ENERGY-GLOBAL-2027-v1.0.0
- Latest version
- resolve the concept DOI or the registry record
- Correction route
- Registry correction pathway
- Notice types
- erratum · addendum · supersession · withdrawal
C.3Corrections log
0correction notices. No edition has been released yet, so none can be corrected; the log below lists each edition’s current version.
| Edition | Version | Date | State | Change | Notice |
|---|---|---|---|---|---|
| GS-02 | NR-SECTOR-ENERGY-GLOBAL-2026-BASELINE-v1.0.0 | October 2026 | Draft | Baseline Edition 2026, inaugural annual edition, | None |
Notice types: erratum, addendum, supersession, withdrawal. A correction is a new version with a published notice; the earlier version stays resolvable, and no edition is ever edited in silence.
C.4Open record
This edition’s open record
- Publication ID
- NR-SECTOR-ENERGY-GLOBAL-2026-BASELINE-v1.0.0
- Desk identifier and series alias
- NR-SEC-GS-02-2026-BL
- Collection
- None
- DOI
- Concept and version DOI at deposit, on Zenodo with DataCite metadata
- Versions
- Each correction is a new version (isNewVersionOf); the concept DOI resolves to the latest
- Bundle
- RO-Crate 1.2 with CITATION.cff, CodeMeta and PROV-O provenance; a signed manifest
- Licence
- CC BY 4.0 (SPDX CC-BY-4.0) for original material; metadata CC0 1.0
Credit and identity
- ORCID
- Your iD in the deposit and the contribution record; DataCite can then add the work to your ORCID record
- ROR
- Your organisation by its ROR identifier, never by a typed name alone
- CRediT
- Conceptualization, Data curation, Formal analysis, Investigation, Methodology, Software, Validation, Visualisation, Writing, review and editing
- Account
- None needed to contribute; never a password
Find and follow
Search the open indexes for Global Energy; software is cited by its SWHID from Software Heritage, and a quantified scenario run is preregistered on OSF before it is run. Annotation is your choice: Hypothesis opens this page in its own viewer.
Mirrors and harvest
The DOI is canonical. At release each signed bundle is also given an IPFS content identifier and a bloxberg anchor as mirrors; both are listed in the record once they exist. Zenodo exposes every record over OAI-PMH, and reviews and endorsements can arrive through COAR Notify where the repository supports it.
{
"metadata": {
"resource_type": {
"id": "dataset"
},
"title": "Evidence on Global Energy for Nexus Reports",
"publication_date": "YYYY-MM-DD",
"creators": [
{
"person_or_org": {
"type": "personal",
"family_name": "Your family name",
"given_name": "Your given name",
"identifiers": [
{
"scheme": "orcid",
"identifier": "0000-0000-0000-0000"
}
]
},
"affiliations": [
{
"id": "ROR identifier of your organisation"
}
]
}
],
"description": "What it is, where its record is kept and how it bears on Global Energy Risk and Resilience Report 2026: Baseline Edition, The State of the World’s Energy System..",
"rights": [
{
"id": "cc-by-4.0"
}
],
"subjects": [
{
"subject": "Nexus Reports"
},
{
"subject": "Global Energy"
},
{
"subject": "Global Sector Report · GS-02"
}
],
"related_identifiers": [
{
"identifier": "https://therisk.global/nexus-reports/editions/gs-02/",
"scheme": "url",
"relation_type": {
"id": "issupplementto"
},
"resource_type": {
"id": "publication-report"
}
}
],
"version": "1.0.0"
},
"custom_fields": {},
"access": {
"record": "public",
"files": "public"
},
"files": {
"enabled": true
},
"parent": {
"communities": {
"default": "nexusreports"
}
}
}C.5Where this edition sits among the six pillars
Foundry seals the evidence and Universe tests it; Reports publishes it; Standards takes its corrections and Academy teaches from it.
- F03 Sealed observations and indicator series Foundry Sealed observations and indicator series behind a profile (closeout).
- F04 After-action and scenario findings for Universe After-action and scenario findings for chapters 10 and 13 (after action review).
- F05 National Portfolio movement for chapter Foundry National Portfolio movement for chapter 11 (after action review).
- Applied in editions Standards Nexus Standards: applied in editions.
- GS-02 edition Reports Global Energy 2026, published in every format with its sources, citation and corrections.
- F06 Method and correction findings as change Standards Method and correction findings as change proposals (correction).
- F12 Q4 synthesis informs the next-year Universe Q4 synthesis informs the next-year mandate (renewal).
- Taught in the open Academy Risk Academy: taught in the open.
What Foundry and Universe hand to this edition, and what it hands to Standards, Universe and Academy. From the programme spine; GS-02 is a drafted Baseline Edition, so these handoffs run from its first operational quarter.
| Handoff | Between | What crosses, and when |
|---|---|---|
| F03 | Foundry to Reports | Sealed observations and indicator series behind a profile (closeout). |
| F04 | Universe to Reports | After-action and scenario findings for chapters 10 and 13 (after action review). |
| F05 | Foundry to Reports | National Portfolio movement for chapter 11 (after action review). |
| Ring | Nexus Standards to Reports | Nexus Standards: applied in editions. |
| F06 | Reports to Nexus Standards | Method and correction findings as change proposals (correction). |
| F12 | Reports to Universe | Q4 synthesis informs the next-year mandate (renewal). |
| Ring | Reports to Risk Academy | Risk Academy: taught in the open. |